C6 — Time Reporting System: the release plan

Tracking block — case day. Read the Case rules (on Moodle) and the Case rules, part 2 (on Moodle) first. They give the shape of the day, the slide format and the grading. This sheet has only what is specific to this case. Date, time and room are on Moodle.

Case: Time Reporting System — System Description (from C4), with this sheet. The contract, the payments, the team and the deadline are in §7 and §9 of the description. Adapted from Eduardo Miranda’s TRS milestone assignment (2013) and his Buffered MoSCoW Rules (2011).

Before the day. Read Miranda’s paper — five pages. Sketch which features depend on which. Check whether the safe total in Tables 1 and 2 fits the capacity at all. Bring both to slot 1.

Readings

Everything you need is in the description, this sheet and these.

Objectives

Decide what TRS can promise for 1 June, and set the plan up so that a slip shows in the week it happens. In C5 the scope was fixed and you found the date. Here the date is fixed, and the scope moves.

Your situation

It is Monday 11 January 2027, the kick-off. TRS must be live no later than Tuesday 1 June 2027 (§9). Instead of C5’s plan-driven increment, the work runs in three time boxes of four weeks. Your C5 chain took about eight weeks for ten features. A time box has four.

Calendar. Ignore public holidays.

Step Fact
Specification Your team writes it in 2 weeks. The client approves it in 1 week. These hours are outside the iterations
Iterations Three, 4 weeks each, back to back, from the Monday after approval. Each ends with a demonstration
Acceptance The client’s IT department tests for 2 weeks. It needs the test procedure 1 week before
Training The client’s HR department trains for 1 week, before launch. It needs the material 2 weeks before
Data migration The client’s IT department sends the CSV files 1 week before launch
Support 30 days after launch

Capacity. The team of §9. The two developers give 320 hours per iteration (2 × 40 h × 4 weeks). Out of those hours, each iteration also needs 30 hours of requirements and design and 20 hours for the demonstration. Testing and documentation, 40 hours per iteration, are the tester’s.

Two estimates per feature. Normal has a fair chance of being enough. Safe is enough except in a few really bad cases.

Table 1 — Features, ranked by the client by business value

Rank Feature Normal (h) Safe (h)
1 Login 24 32
2 Grant Account Access 24 32
3 Create Pay Code 24 32
4 Create Charge Authorization 40 56
5 Report Time 40 56
6 Submit Time Sheet 32 40
7 Approve Time Sheet 32 40
8 Block Account 24 32
9 Reset Password 24 32
10 Revoke Account Access 24 32
11 Update Pay Code 24 32
12 Delete Pay Code 24 32
13 Modify Time Sheet 32 40
14 Recall Time Sheet 32 40
15 Delete Charge Authorization 24 32
16 Delegate Approval 32 40
17 Revoke Delegation 32 40
18 Supervisor Report 40 56
19 Employee Report 40 56

Table 2 — Features the client did not rank

The description requires them (§2, §7). The client treats them as given.

Feature Normal (h) Safe (h)
Synchronize Employee Data 40 56
Export Approved Time Sheets 40 56
Import Legacy Data 32 48

The dependencies among the first ten features are in C5’s Table 1. The rest are yours.

Questions to answer

  1. Plan the release with Buffered MoSCoW. Draw the feature dependency graph, and place the three features of Table 2 in it. Decide whether you commit per iteration or once for the release, and say why. Then fill each time box as Miranda does: Musts at their safe estimates, then the Must buffer, then Shoulds and Coulds inside the buffer above them. Give the iteration planning table in the format of Table 3.
  2. Build the milestone plan, from kick-off to the end of support. Each milestone is a result, not an activity, and has a date and an owner, the client’s own milestones included. Attach every payment in §7.1 to a milestone. Use the format of Table 4.
  3. Decide what ships by 1 June. Which features are Musts, which are at risk, and which will not make it? Is a four-week time box long enough to demonstrate something useful each time? Do you renegotiate the date, the scope or the team, and what does each option cost?
  4. Track it. Which milestone or buffer do you watch, what reading makes you act, and what do you drop first? How should the contract reward the Shoulds and Coulds, so that a buffer left over is not simply spent?

Every reason must rest on a concept from L6a, L5a or L6b, used the way the lecture defines it.

Table 3 — Iteration planning table (format)

Feature Rank Normal (h) Safe (h) Must / Should / Could / Won’t Iteration
…          

Table 4 — Milestone chart (format)

Date Path / results / stakeholder … Path / results / stakeholder Description Responsible
Project start          
…          
Project end          

Minto on this case

Your answer to question 3 is slide 2. Questions 1 and 2 give the reasons under it. Question 4 is slide 7. Slide 8 is the assumption that would change your answer, for example safe estimates hit in every feature at once.

The full iteration table and the full milestone chart go in backup and in the appendix.

Deliverables

Slides (8 max) on Moodle before the presentations start, Fri 4 Dec. Report (5 pages max) and final slides Thu 10 Dec, 23:59. Both PDF. See the Case rules (on Moodle) and part 2.

Where teams lose points on this case


Acknowledgments

The Time Reporting System, its description and the three assignments are adapted from Eduardo Miranda’s course material on estimating and planning software projects (TRS description 2009; critical-path and milestone assignments 2013), taught with David Root.

Sources


Disclaimer: AI is used for text summarization, polishing and explaining. Authors have verified all facts and claims. In case of an error, feel free to file an issue.