Tracking block — case day. Read the Case rules (on Moodle) and the Case rules, part 2 (on Moodle) first. They give the shape of the day, the slide format and the grading. This sheet has only what is specific to this case. Date, time and room are on Moodle.
Case: Time Reporting System — System Description (from C4), with this sheet. The contract, the payments, the team and the deadline are in §7 and §9 of the description. Adapted from Eduardo Miranda’s TRS milestone assignment (2013) and his Buffered MoSCoW Rules (2011).
Before the day. Read Miranda’s paper — five pages. Sketch which features depend on which. Check whether the safe total in Tables 1 and 2 fits the capacity at all. Bring both to slot 1.
Everything you need is in the description, this sheet and these.
Decide what TRS can promise for 1 June, and set the plan up so that a slip shows in the week it happens. In C5 the scope was fixed and you found the date. Here the date is fixed, and the scope moves.
It is Monday 11 January 2027, the kick-off. TRS must be live no later than Tuesday 1 June 2027 (§9). Instead of C5’s plan-driven increment, the work runs in three time boxes of four weeks. Your C5 chain took about eight weeks for ten features. A time box has four.
Calendar. Ignore public holidays.
| Step | Fact |
|---|---|
| Specification | Your team writes it in 2 weeks. The client approves it in 1 week. These hours are outside the iterations |
| Iterations | Three, 4 weeks each, back to back, from the Monday after approval. Each ends with a demonstration |
| Acceptance | The client’s IT department tests for 2 weeks. It needs the test procedure 1 week before |
| Training | The client’s HR department trains for 1 week, before launch. It needs the material 2 weeks before |
| Data migration | The client’s IT department sends the CSV files 1 week before launch |
| Support | 30 days after launch |
Capacity. The team of §9. The two developers give 320 hours per iteration (2 × 40 h × 4 weeks). Out of those hours, each iteration also needs 30 hours of requirements and design and 20 hours for the demonstration. Testing and documentation, 40 hours per iteration, are the tester’s.
Two estimates per feature. Normal has a fair chance of being enough. Safe is enough except in a few really bad cases.
| Rank | Feature | Normal (h) | Safe (h) |
|---|---|---|---|
| 1 | Login | 24 | 32 |
| 2 | Grant Account Access | 24 | 32 |
| 3 | Create Pay Code | 24 | 32 |
| 4 | Create Charge Authorization | 40 | 56 |
| 5 | Report Time | 40 | 56 |
| 6 | Submit Time Sheet | 32 | 40 |
| 7 | Approve Time Sheet | 32 | 40 |
| 8 | Block Account | 24 | 32 |
| 9 | Reset Password | 24 | 32 |
| 10 | Revoke Account Access | 24 | 32 |
| 11 | Update Pay Code | 24 | 32 |
| 12 | Delete Pay Code | 24 | 32 |
| 13 | Modify Time Sheet | 32 | 40 |
| 14 | Recall Time Sheet | 32 | 40 |
| 15 | Delete Charge Authorization | 24 | 32 |
| 16 | Delegate Approval | 32 | 40 |
| 17 | Revoke Delegation | 32 | 40 |
| 18 | Supervisor Report | 40 | 56 |
| 19 | Employee Report | 40 | 56 |
The description requires them (§2, §7). The client treats them as given.
| Feature | Normal (h) | Safe (h) |
|---|---|---|
| Synchronize Employee Data | 40 | 56 |
| Export Approved Time Sheets | 40 | 56 |
| Import Legacy Data | 32 | 48 |
The dependencies among the first ten features are in C5’s Table 1. The rest are yours.
Every reason must rest on a concept from L6a, L5a or L6b, used the way the lecture defines it.
| Feature | Rank | Normal (h) | Safe (h) | Must / Should / Could / Won’t | Iteration |
|---|---|---|---|---|---|
| … |
| Date | Path / results / stakeholder | … | Path / results / stakeholder | Description | Responsible |
|---|---|---|---|---|---|
| Project start | |||||
| … | |||||
| Project end |
Your answer to question 3 is slide 2. Questions 1 and 2 give the reasons under it. Question 4 is slide 7. Slide 8 is the assumption that would change your answer, for example safe estimates hit in every feature at once.
The full iteration table and the full milestone chart go in backup and in the appendix.
Slides (8 max) on Moodle before the presentations start, Fri 4 Dec. Report (5 pages max) and final slides Thu 10 Dec, 23:59. Both PDF. See the Case rules (on Moodle) and part 2.
The Time Reporting System, its description and the three assignments are adapted from Eduardo Miranda’s course material on estimating and planning software projects (TRS description 2009; critical-path and milestone assignments 2013), taught with David Root.