C5 — Time Reporting System: the first increment

Planning block — case day. Read the Case rules (on Moodle) and the Case rules, part 2 (on Moodle) first. They give the shape of the day, the slide format and the grading. This sheet has only what is specific to this case. Date, time and room are on Moodle.

Case: Time Reporting System — System Description (from C4), with this sheet. The team, the start date and the payment for each demonstration are in §7 and §9 of the description. Adapted from Eduardo Miranda’s TRS critical-path assignment (2013).

Before the day. Read Tables 1 and 2. The features’ order is given. The order of the eight increment activities is not: draft it, one reason per dependency. Bring the draft to slot 1. The recitation shows how to turn it into a network.

Readings

Everything you need is in the description, this sheet and these.

Objectives

Turn one increment into a schedule the client can rely on, and promise the date of its demonstration. This case is about order, time and people. What goes into the increment is fixed below. Choosing it is C6.

Your situation

Your company won the contract. Development starts Monday 1 February 2027. The client pays 20% at the demonstration of each increment, and asks you for the date of the first one.

The first increment carries the ten features in Table 1. This plan is plan-driven: the scope is fixed, and the date is what you must find. Each feature is scheduled separately, to make tracking and reprioritisation easier. Integration happens as each feature is finished, inside its estimate.

The team is in §9: two developers and one tester. Day 1 is Monday 1 February. Count working days, Monday to Friday, and ignore public holidays.

Two estimates per task. Normal has a fair chance of being enough. Safe is enough except in a few really bad cases.

Table 1 — Features: effort, duration and dependencies

Each feature is built by one developer. Requires lists the features that must be finished first.

Feature Effort (person-hours) Normal (days) Safe (days) Requires
Login 24 3 4 —
Grant Account Access 24 3 4 Login
Revoke Account Access 24 3 4 Grant Account Access
Block Account 24 3 4 Grant Account Access
Reset Password 24 3 4 Grant Account Access
Create Pay Code 24 3 4 Grant Account Access
Create Charge Authorization 40 5 7 Create Pay Code
Report Time 40 5 7 Create Charge Authorization
Submit Time Sheet 32 4 5 Report Time
Approve Time Sheet 32 4 5 Submit Time Sheet

In this increment, employee data is loaded by hand from a file. The interfaces of §2 come later.

Table 2 — Increment activities: who, effort and duration

The order of these eight activities is yours to decide.

Activity Who Effort (person-hours) Normal (days) Safe (days)
Requirements review one developer 16 2 3
Increment design both developers 80 5 7
Design review whole team 24 1 1
System test case design tester 40 5 7
System test execution tester 16 2 3
Update documentation tester 24 3 4
Conduct demonstration whole team 24 1 1
Fix remaining problems whole team 24 1 2

Questions to answer

  1. Build the network. Use the dependencies in Table 1. Add your own for Table 2, one reason each, tagged [A]. Draw it, or give it as a dependency table.
  2. Find the critical path. Make the two passes at normal durations. For every task give early start, early finish, late start, late finish, total float and free float. Which tasks are critical? How long could the design review start late without moving the demonstration? How long could Approve Time Sheet start late without delaying the task after it? Would a shorter test case design shorten the increment? Say why.
  3. Find the critical chain. Now count the people. Where would one person be needed in two places at once? Sequence those tasks. The longest path through tasks and people is the critical chain. Is it the same as the critical path? If not, who sets the date?
  4. Promise the date. Plan the chain at normal durations. Size a project buffer from the gap between safe and normal, and say how you sized it. Put feeding buffers where other paths join the chain. Then give the demonstration date on the calendar. Show that it passes the four tests of a milestone, and say whether it is a hard or a soft date, and for whom. How will you watch the buffer, and what will you do as each third of it is used?

Every reason must rest on a concept from L5a or L5b, used the way the lecture defines it.

Minto on this case

The date in question 4 is slide 2. Questions 2 and 3 give the reasons under it. The buffer rule in question 4 is slide 7: who watches it, how often, and what happens at each third. Slide 8 is the assumption that would move the date most.

The full network and the full table of values go in backup and in the appendix.

Deliverables

Slides (8 max) on Moodle before the presentations start, Fri 20 Nov. Report (5 pages max) and final slides Thu 26 Nov, 23:59. Both PDF. See the Case rules (on Moodle) and part 2.

Where teams lose points on this case


Acknowledgments

The Time Reporting System, its description and the three assignments are adapted from Eduardo Miranda’s course material on estimating and planning software projects (TRS description 2009; critical-path and milestone assignments 2013), taught with David Root.

Sources


Disclaimer: AI is used for text summarization, polishing and explaining. Authors have verified all facts and claims. In case of an error, feel free to file an issue.