Planning Poker – Structured Expert Estimation Technique
1. Why We Need Structured Estimation
Unaided expert estimation often fails because it depends on intuition and tacit knowledge that’s hard to explain or verify. This leads to cognitive and group biases:
| Bias Type | Description | Example |
|---|---|---|
| Availability | Recent or vivid experiences dominate judgment. | “This sprint took forever; this one will too.” |
| Anchoring | First number mentioned influences others. | “Last project was 100 days → probably similar.” |
| Representativeness | Ignoring actual data, assuming similar tasks take similar time. | “It’s another login feature, so same effort.” |
| Confirmation | Seeking only evidence that supports initial belief. | “My estimate seems right; I’ll skip checking.” |
| Groupthink / Conformity | People align with the dominant opinion. | Junior devs agree with senior’s estimate. |
Structured group estimation methods—like Wideband Delphi, Successive Approximations, Planning Poker, and Paired Comparisons—are designed to counter these biases by making reasoning explicit, collective, and repeatable.
2. Purpose of Group Estimation
Group estimation works only if everyone shares a common understanding of what’s being estimated:
- Are assumptions and ground rules clear?
- Is the definition of “done” shared?
e.g., “Work is done when code is checked in, unit tests pass, and documentation is written.”
- Does the estimate include rework and support tasks?
- Is the work broken down enough to avoid missing or double-counting tasks?
This shared understanding prevents many classic estimation errors.
3. What Is Planning Poker
- Proposed by: James Grenning (2002)
- Popularized by: Mike Cohn (2005)
- Type: Group, iterative estimation process.
- Origin: A simplified version of Wideband Delphi for Agile teams.
- Use:
- Early in release planning (for sizing and prioritizing stories).
- Complemented later by detailed task planning at iteration start.
4. What It Estimates
| Mode | What It Measures | Best For | Example Unit |
|---|---|---|---|
| Ideal Days | Pure effort assuming no interruptions or dependencies. | Non-recurrent tasks (e.g., system design, integration). | “3 ideal days” = full-time work for one dev. |
| Story Points | Relative size/complexity vs. a reference story. | Comparable, recurring tasks (e.g., coding features). | “Story A = 3 points, Story B = 8 points.” |
Start by agreeing on a baseline story (medium complexity).
Example: assign it 3 or 5 points and compare all others against it.
5. Planning Poker Procedures: Standard vs. Miranda’s Enhanced Version
| Step | Standard Planning Poker (Grenning 2002 / Cohn 2005) | Eduardo Miranda’s Enhanced Version (2008) |
|---|---|---|
| 1. Preparation | Each estimator receives a deck of cards showing possible estimates (typically Fibonacci numbers: 1, 2, 3, 5, 8, 13, 20…). | Same, but first select a baseline story of medium complexity (assigned 3 or 5 points) to ensure consistent relative sizing. |
| 2. Story presentation | Product Owner reads the user story; team discusses scope, assumptions, and acceptance criteria briefly. | Same, but emphasize clarifying what is included in the estimate (e.g., testing, documentation, integration). |
| 3. Private estimation | Each estimator secretly selects one card representing their estimate. | Same — estimators select a card individually and privately. |
| 4. Reveal | All cards are revealed simultaneously to avoid anchoring bias. | Same simultaneous reveal, but note that identical numbers may come from different reasoning. |
| 5. Discussion | Discuss differences — particularly highest and lowest values — to uncover differing assumptions. | Discuss both differences and coincidences, ensuring shared understanding even when estimates match. |
| 6. Re-estimate | A new round of estimation and reveal occurs until estimates converge or reach consensus. | Re-estimate one more time, allowing estimators to reconsider based on the discussion. |
| 7. Final check | Team agrees on a consensus value (or uses an average). | After one final reflection, estimators may change their estimates one last time before recording final values. |
| 8. Recording results | Record the final team estimate. | Record each estimator’s final individual estimate to retain spread information. |
| 9. Post-session review | None formally prescribed. | After all stories are estimated, review recorded values: • Compute a mean for each story. • Investigate stories showing unusual disagreement rather than averaging blindly. |
| Focus | Efficiency and quick team convergence. | Deeper understanding, validation of reasoning, and identification of inconsistent judgments. |
6. Strengths of Planning Poker
- Uses the collective knowledge of the whole team.
- Reduces anchoring and conformity by keeping initial estimates secret.
- Builds a shared understanding of the work.
- Encourages relative thinking (compare against known stories).
- Focuses discussion only where there are real differences.
- Builds commitment and ownership among estimators.
7. Weaknesses and Limitations of Planning Poker
- Lack of External Calibration
Planning Poker depends entirely on the team’s internal experience. There is no external benchmark or use of historical data, which makes estimates subjective and potentially inconsistent across projects. - Relative Sizing Drift
Because Planning Poker uses relative estimation, the meaning of a “3” or “5” can shift over time. If the baseline story isn’t well defined or periodically revisited, the team gradually loses consistency in how it interprets story points. - Hidden Disagreement
Even when all team members choose the same number, they may have different reasons for doing so. Without probing those rationales, agreement on the number can hide genuine differences in understanding of scope or complexity. - Lack of Cross-Project Consistency
Since estimates are relative and team-specific, they cannot be compared reliably across different teams or projects. A “5” in one team might represent a very different effort than a “5” in another. - No Formal Method for Combining Estimates
The process doesn’t specify how to merge or average estimates once they’re collected. Simple averaging can distort results, especially when there are outliers or wide uncertainty ranges. - Poor Fit for Architectural or Infrastructure Work
Planning Poker works best for user stories of similar type and scope. Architectural tasks, infrastructure setup, or research spikes are difficult to relate to story size, making relative estimation unreliable for those items.
8. Example
User Story: “As a user, I can reset my password by email.”
Team Process:
- Discuss dependencies (email API, UI form, validation).
- Everyone chooses a card →
- Dev A: 3, Dev B: 5, Dev C: 8.
- Reveal cards → discuss why C chose 8 (mentions multi-language templates).
- New round → all pick 5.
- Final estimate: 5 story points.
9. Summary Table
| Aspect | Planning Poker | Wideband Delphi |
|---|---|---|
| Participants | Whole team | Selected experts |
| Rounds | Few (1–3) | Several (3–5) |
| Communication | Open discussion | Anonymized feedback between rounds |
| Output | Consensus or mean estimate | Aggregated expert estimate |
| Typical Context | Agile sprint/release planning | Early project estimation |
Sources
Cohn, Mike. Agile estimating and planning. Pearson Education, 2005.