Risk Identification

*Adapted from David Root (2014)


Key Concepts

  • A concern is where risk identification starts — something uneasy, uncertain.
  • Risks are uncertain future events or conditions, BEFORE they become issues. Once realized, they are issues/problems.
  • Identification comes from many inputs: meetings, artifacts (design docs, requirements, test plans), past/historical data, stakeholder communication.

Techniques & Process

Technique Description / Best Practices
Brainstorming / Workshops Assemble group of people with different perspectives. Have a facilitator, scribe, timekeeper. Everyone contributes ideas without debate first; organize later. Use checklists/taxonomies to prompt ideas.
Review of Artifacts Requirements docs, design docs, test plans etc. Check for ambiguities, omissions, dependencies, constraints.
Interviews / Stakeholder Input Ask domain experts, end users, operational staff about things that worry them. Often uncover external or business risks.
Historical / Lessons Learned Examine past projects: what went wrong, what surprised people. Helps find known risk categories.
Formal Methods SEI-SRE, risk taxonomy questionnaires, PROMPT lists. Quantitative/qualitative risk methods.

When & Who

  • Identification is ongoing: it should not be a one-time step. As project evolves, new risks can emerge.
  • Everyone participates, not just project manager: technical team, QA, operations, stakeholders, customers.
  • Could have dedicated risk‐identification meetings, but also leverage routine meetings (e.g. design reviews, requirements reviews) to spot risks.

Risk Statements


Structure of a Good Risk Statement

From several sources (DoD RIO, PRINCE2, DAU etc.) the attributes are:

Component What it is
Condition / Cause / Root Cause The situation or trigger that gives rise to risk. A fact / internal or external cause.
Event / Potential Event The uncertain occurrence or situation that might happen (the risk itself).
Consequence / Effect / Impact What will happen if the risk event occurs. The negative outcomes.

Sometimes cause may be optional or less known; event and consequence are essential.


Formats & Templates

  • If-Then format: “If [event/condition], then [consequence/impact].” Optionally include cause.
    E.g. If key vendor fails to deliver components on time, then project schedule will slip by X days and costs will increase.
  • Cause-Event-Effect (PRINCE2): “Due to [cause], there is a threat/event that [event] which would lead to [effect].”
  • Sometimes other variants: “Because …, so …, which would …” to reflect PRINCE2 threat/opportunity format.

Do’s and Don’ts in Risk Statements

Do’s Don’ts
Do write short (< ~30 words), fact-based, actionable statements. Focus on what is / what could be, not hypothetical “what if” speculation. Include cause when known. Don’t use vague phrasing (“might”, “could” without clarity), lots of acronyms/abbreviations, generalizations. Don’t bundle multiple risks in one statement. Don’t put mitigation or solution into the statement. Don’t push consequence too far out (“in 5 years we’ll be bankrupt”) unless relevant.
Do ensure source of condition (internal or external). Don’t mix issues (past) with risks (future).
Do focus on a single risk per statement. Don’t include uncertain cause + effect in a muddled way; clarity suffers if cause/event/effect are not distinguishable.

Context & Supporting Information

  • Risk statement gives the core elements, but context gives background: what leads to the condition; related events; who is involved; environment / constraints; triggers if any.
  • Also assign owner (who is responsible), timeframe (when risk might occur), probability / likelihood, impact scale.

Examples

Example Good / Bad Why
“The budget for the project is not yet defined.” Weak It’s more of a problem / missing plan. Doesn’t have event or consequence, and not clearly actionable.
“Requirements might change.” Weak Vague: which requirements, why, what impact.
“Because key vendor’s lead time is uncertain (cause), there is a risk that component delivery will be delayed (event), which would delay system integration and increase costs (effect).” Good Clear cause, event, effect.
PRINCE2 style: “Due to the heavy rain (cause), there is a threat that fields might be flooded (event), which would damage the crops (effect).”    

Acknowledgments

This content is heavily inspired by and adapted from lectures by Eduardo Miranda and David Root on software project management. The structure, examples, and pedagogical approach reflect their teaching materials and frameworks.


Sources

  • DEPARTMENT OF ENERGY software risk management guide (SQAS21.01.00) — gives process, forms, templates. energy.gov
  • PRINCE2 Risk Theme (Cause-Event-Effect) for how to articulate and manage risk statements. prince2.wiki projex.com
  • DoD RIO Guide — best practices on risk statement including cause / event / consequence. dau.edu

  • Root, David. Managing Software Development. Lecture materials, 2014.