Estimates

An estimate turns scope into resources and time: how big the software is, how much effort it takes, how long it runs and what it costs. Estimates are wrong by an amount known well enough to plan for. Across ten industrial surveys, “most projects (60-80%) are completed over budget and/or schedule”, and the likely average overrun is “between 30 and 40%” [1].

That is why no method is trusted alone. The pages below each describe one method; Estimation approaches lays out the six families, the cost estimating relationship behind every model, and how to combine methods when requirements are vague and there is no history.

Which page to open

Page Good for Best fit Main cost
Estimation approaches choosing and combining methods vague requirements, no history none: it is the map
Expert judgment knowledge no model can take in early or unusual work anchoring and over-optimism
Planning Poker fast team sizing of a backlog release planning of familiar stories the first-round cards fence the result
Paired comparison consistent relative sizes, with a check early sizing; items unlike the rest many comparisons, and a reference of known size
Function point analysis a defensible size from requirements a written specification counting effort and trained counters
FPA explained the counting rules, worked through learning to count time to learn the rules
COCOMO effort and schedule from size and cost drivers a size, and past projects to calibrate on calibration data
COCOMO II drivers the rating values for scale factors and effort multipliers applying COCOMO II rating each driver honestly

The table has no accuracy column on purpose. Across 15 studies comparing experts with models, five favoured experts, five found no difference and five favoured models [2]. What decides is calibration: Basic COCOMO landed within a factor of 1.3 of actuals 29% of the time, and the version with 15 cost drivers 78% [3].

How solid is this?

  • The 30–40% is an order of magnitude, from surveys with no random samples, mostly of managers reporting on their own projects.
  • The 29% and 78% are Boehm’s own figures, quoted in a debate he was arguing, from 63 projects.

Acknowledgments

This page adapts material from lectures by Eduardo Miranda and David Root [4] on software project management.

References

  1. K. Moløkken and M. Jørgensen,
    “A Review of Surveys on Software Effort Estimation,” in Proceedings of the 2003 International Symposium on Empirical Software Engineering (ISESE 2003), IEEE Computer Society, 2003, pp. 223–230. doi: 10.1109/ISESE.2003.1237981.
  2. M. Jørgensen,
    “A Review of Studies on Expert Estimation of Software Development Effort,” Journal of Systems and Software, vol. 70, no. 1–2, pp. 37–60, Feb. 2004, doi: 10.1016/S0164-1212(02)00156-5.
  3. M. Jørgensen, B. Boehm, and S. Rifkin,
    “Software Development Effort Estimation: Formal Models or Expert Judgment?,” IEEE Software, vol. 26, no. 2, pp. 14–19, Mar. 2009, doi: 10.1109/MS.2009.47.
  4. D. Root,
    Managing Software Development. Carnegie Mellon University / Innopolis University lecture series, 2014.

Disclaimer: AI is used for text summarization, polishing and explaining. Authors have verified all facts and claims. In case of an error, feel free to file an issue.