SN L4a — Work Breakdown Structure

A revision summary of the first Scope lecture. A work breakdown structure (WBS) is the whole project cut into pieces that someone can own, estimate and track. The lecture gives one to Quill 1.0, the invented word processor from the requirements and risk lectures: a publishing-house customer, six people, release due 1 February, 500-page documents open within 2 seconds, citations, PDF export, cloud sync, documents in the customer’s EU data centre. Three worries come with it: the vendor of the PDF engine is late, only Dana understands the citation engine, and tracked changes are already requested for Quill 2.0. Each section links to the handbook page carrying the detail and the sources.

Why bother? One software project, followed for 42 weeks and reported in a review of time prediction, planned 96 development tasks, then added 83 and deleted 46 [1]. So list every piece of work you can foresee, and plan to keep the list up to date.

1. What a WBS is

PMI defines it as “a deliverable-oriented grouping of project elements that organizes and defines the total work scope of the project” [2]. A bicycle splits into frame set, crank set and wheels, the frame set into frame, fork and seat; an outline (1, 1.1, 1.1.1) carries the same tree.

One rule holds it together, the 100% rule: every level holds all the work of its parent, and nothing else. It fails two ways, with two victims. Leave work out and the project pays: it “will almost certainly be delayed and may experience cost overruns”. Put work in twice, or unasked, and the customer pays: “the customer’s time and money will be wasted” [2]. In a first draft of Quill’s tree the document store appears under both Citations and Cloud sync, so it is estimated twice; the acceptance run at the publisher appears nowhere. NASA’s cardinal rule faces the contract: “Work scope not contained in the project WBS should not be considered part of the project” [3]. If in doubt, include it, and let the customer confirm or discard it [4].

A network of tasks is not a WBS. “The WBS is NOT a schedule, and is developed before the project team develops a timeline for the project” [5]. The WBS says what, and whose; the network says how, and when, and its tasks come from the WBS leaves.

Scrum builds the same tree with size labels [6]: epic (months), feature (weeks), story (days), task (hours). For example, epic Citations, feature Publisher styles, story “As an editor I want references in the house style”. Stories say what, tasks say how, so the scope tree ends at the story. A theme is a group of related stories, not a level.

The unit of the tree is the work package: one deliverable plus the work that makes it, with one owner. In the new-bike WBS, Fork: design, build, test is one. Design and integration serve all the bicycle’s parts, so they sit beside them; project management serves everything, so it sits at the top [4].

A new-bike project as a WBS: the bicycle and its assemblies, manufacturing instructions, sourcing, a marketing campaign and project management

→ WBS · Building a WBS

2. Orientation

The criterion that splits the top is the orientation: by deliverable (what will I get, what does each piece cost?), by task or phase (what happens when?), by discipline (who does the work?), by account, or a hybrid [4]. Globerson calls the WBS “the taxonomy of a project” [7]: the leaves stay the same, and the top decides what one glance shows.

Sponsors read deliverables. An ambulance-dispatch system drawn by product (call taking, ambulance allocation, ambulance communication) tells the sponsor you understand the scope of my project; drawn by phase, it says only you know how to do your job. Drop ambulance communication and the product tree loses one branch with its cost; in the phase tree, fractions of design, development, deployment and training must be dug out. A book makes the same point: chapter 2 sits in one branch of the deliverable tree, three places in the task tree, and nowhere you can point to in the discipline tree. Of six questions about the book, the deliverable tree answers five; the discipline tree wins only who does the copyediting?

There is a case for verbs. Progress is measured on work, and deliverables on a summary Gantt chart “would simply look like the stripes on a prison uniform” [8]. PMI answers that “WBS elements that are not deliverable-focused may lead to project failure” [2]. Both are right, at different levels: nouns at the top, verbs at the leaves. An outcome may contain activities; an activity never contains outcomes. PDF export → set up the vendor engine is fine; Testing → Citations is not.

The grouping also becomes the organisation. Thirty course packages of an MBA curriculum, flat, report to one project manager who must know all thirty subjects; grouped, they sit under six managers who settle most changes themselves [7]. The choice is usually made at proposal time, “sometimes without being aware of it”.

Exam tip: argue orientation from the reader’s question, not from taste: name the question, then show where each tree puts the answer.

→ Orientation

3. Product plus enabling work

NASA’s answer is the hybrid. A product breakdown structure holds only the parts you deliver; the WBS adds the work of putting them together: management, systems engineering, integration and verification, logistics support. “The whole takes more work than the sum of the parts” [9]. So the WBS has elements that are not parts.

A system broken into product components A to D, alongside management, systems engineering, integration and verification, and logistics support

NASA’s template puts shared enabling work at Level 2, beside the products, with system integration and testing as its own element [3]. For Quill: management, systems engineering and QA; then editor, big-document engine, citations, PDF export, cloud sync and document store; then system integration and test, and the release.

The payoff shows when a function is added. In NASA’s sample software project, a new functional unit is one new branch under development, carrying its own design, code and unit test. Four existing elements grow by a visible amount (integration testing, user manuals, the help desk, training), and the nine Level 2 elements stay nine. The new function’s cost reads off a few lines; in a phase tree it spreads across every phase.

Shared work sits beside what it serves. Quill’s document store serves the editor, citations and cloud sync, so it goes at Level 2 beside them; the acceptance run goes under system integration and test; the citation dialog’s design serves citations only, so it goes under Citations. Draw the branch points where you will integrate, or integration has no owner and no cost line [9].

→ NASA

4. Building a WBS

Know five things before drawing a box [4]: the start and end point (Quill ends at acceptance by the publisher), what kind of system it is, its functions and stakeholders, its quality attributes, and a notional architecture. What you do not know, assume, and write the assumption down. Then seven steps: check the scope; split by outcome; add architectural elements that are not features, such as the document store; refine into pieces you can drop; add activities and tasks; review for gaps, overlaps and wrong nesting; and update as you learn.

Every requirement and risk leaves work behind. The 2-second target adds a layout cache and a performance test at 500 pages. The EU data centre adds a set-up package. The vendor’s PDF engine must be selected, learned, set up, adapted and interfaced, and licensed: reused code is not free. And the mitigation for Dana’s knowledge, pairing on citations, is work: if it is not in the tree, nobody does it.

Stop when a leaf has one owner, can be estimated and its status measured, can be prioritised, scheduled or dropped on its own, and runs under about two weeks, Wysocki’s rule of thumb [8]. Depth follows risk: go deeper on the big-document engine than on editor styles. Every extra level costs maintenance and reporting [2].

Estimates miss the work nobody codes: “when they’ve been ordered to develop a product in the shortest possible time, they don’t go out of their way to look for extra tasks” [10]: cutover, data conversion, installation, demos, QA coordination, meetings, training, holidays. Quill’s first draft forgot the demos, the QA coordination and the winter break. Give each a branch before anyone estimates.

→ Building a WBS · PMI

5. Rolling wave

Detail the next wave, keep the rest coarse: the top covers the whole project from day one, and the bottom fills in one wave at a time [5]. A wave is as long as you can see. Githens’s boat crosses 90 to 110 miles of unknown sea with a 20-mile horizon, so it re-charts its course at least five times.

Far-term work is a planning package: “A WP provides further detail on work content that is considered near-term, while a PP defines far-term work at a summary level” [3]. It has an owner, a budget and a date, and is estimated top-down; without the budget the estimate has a hole that looks like a plan. Quill 2.0’s tracked changes is one. Because it threatens the 2-second promise, wave 1 carries one work package under it, a prototype on a 500-page document: do not detail the guess, schedule the learning. The replanning itself is a work package with a fixed date, or it never happens.

Quill as a rolling-wave WBS: version 1.0 decomposed, version 2.0 a dashed planning package with one prototype work package, and a replanning work package with a fixed date

→ Planning waves

6. Keeping the WBS alive

Every element gets a dictionary entry, which exists for “ensuring that all work scope has been identified and to eliminate duplication and overlap” [3]. Quill’s 1.7 PDF export: content, the vendor engine’s five kinds of work and the licence; owner, Lev; depends on the vendor’s next release; done when a 500-page manuscript exports with all page breaks.

Projects have several dimensions, and a tree shows one per level. With two sponsors and three releases, either order works, but the second axis repeats under the first. The cleaner answer: put one dimension in the tree and tag the rest. Each leaf belongs to exactly one category in every dimension, so any grouping adds up [4], [3].

Keep one master WBS in a tool with stable codes, and change it only through a decision. “If the various WBS structures used are not strictly derived from one basic structure, it will obviously bring chaos to the project” [7]. The 96-task project is why.

Exam tip: the rules here are consensus practice from standards and handbooks, not tested results, and the 96-task project is one project. Quote it as a warning, never as a rate.

→ Building a WBS · Orientation

Practice questions

1. Why does a sponsor prefer a deliverable-oriented WBS, and what does a phase-oriented one do better?

Answer

The sponsor’s questions are about deliverables: what do I get, what does it cost, what if I drop it. A deliverable tree answers each in one branch; a phase tree spreads every answer across all phases. The phase tree shows what happens when, which progress reporting needs, so the hybrid puts those verbs at the leaves [8].

2. Compare the two halves of the 100% rule. Who pays when each is broken?

Answer

Omitted work still has to be done, unplanned, so the project pays in delay and overrun. Duplicated or unrequested work inflates the price, so the customer pays [2]. Either error also makes every total above it wrong.

3. Why should a shared component sit beside the features that use it, not under one of them?

Answer

Under one feature it is owned by the wrong team; under several it is estimated twice. Beside them it is counted once, with one owner, and its integration has a cost line [9].

4. “We use Scrum, so we do not need a WBS.” How would you answer?

Answer

The backlog already is one: epic, feature, story [6]. It ends at the story because tasks say how, not what, and its lower levels are detailed just in time, which is rolling wave by another name.

5. Why is a planning package more than a placeholder?

Answer

It carries an owner, a budget and a date for decomposition. The budget keeps the total honest while the detail waits, so scope is complete without paying for guesses [3].

Where this goes next

Every leaf of Quill’s WBS now has an owner and a definition of done. The publisher asks when, and how much. A WBS tells you what to estimate, not how; that is the next lecture.


Acknowledgments

This content is heavily inspired by and adapted from lectures by Eduardo Miranda and David Root [11] on software project management. The ambulance-dispatch, book-publishing and new-bike examples, the orientations, the building steps and the two-sponsor exercise are Miranda’s [4].

References

  1. T. Halkjelsvik and M. Jørgensen,
    “From Origami to Software Development: A Review of Studies on Judgment-Based Predictions of Performance Time,” Psychological Bulletin, vol. 138, no. 2, pp. 238–271, 2012, doi: 10.1037/a0025996.
  2. Project Management Institute,
    Project Management Institute Practice Standard for Work Breakdown Structures, 1st ed. Project Management Institute, 2001.
  3. National Aeronautics and Space Administration,
    “NASA Work Breakdown Structure (WBS) Handbook,” National Aeronautics and Space Administration, NASA Special Publication NASA/SP-3404, Nov. 2019. [Online]. Available: https://ntrs.nasa.gov/citations/20200000300
  4. E. Miranda,
    “Managing Software Development.” 2014.
  5. G. D. Githens,
    “Rolling Wave Project Planning,” in Proceedings of the 29th Annual Project Management Institute 1998 Seminars & Symposium, Project Management Institute, Oct. 1998. [Online]. Available: https://www.wcu.edu/pmi/1998/NP02.PDF
  6. K. S. Rubin,
    Essential Scrum: A Practical Guide to the Most Popular Agile Process. in Addison-Wesley Signature Series (Cohn). Addison-Wesley Professional, 2012. [Online]. Available: https://innolution.com/essential-scrum
  7. S. Globerson,
    “Impact of various work-breakdown structures on project conceptualization,” International Journal of Project Management, vol. 12, no. 3, pp. 165–171, Aug. 1994, doi: 10.1016/0263-7863(94)90032-9.
  8. R. K. Wysocki and R. McGary,
    Effective Project Management: Traditional, Adaptive, Extreme, 3rd ed. Wiley Publishing, 2003.
  9. NASA,
    “NASA Systems Engineering Handbook,” National Aeronautics and Space Administration, NASA Special Publication SP-2007-6105 Rev1, Dec. 2007. [Online]. Available: https://www.nasa.gov/reference/systems-engineering-handbook/
  10. S. McConnell,
    Rapid development: taming wild software schedules. Pearson Education, 1996.
  11. D. Root,
    Managing Software Development. Carnegie Mellon University / Innopolis University lecture series, 2014.