SN L5b — Activities, Critical Path and Critical Chain
A revision summary of the second Planning lecture. An activity plan is the work under the milestones: who does which task, in what order, and when. The lecture follows Quill, the invented word processor from the requirements and risk lectures, nine weeks before it goes live at the publisher. Three streams merge into one acceptance run: Ana integrates a new PDF engine, then tunes it for 500-page documents; Ivan sets up the EU data centre, then cloud sync; Dana writes ten citation styles, then a reviewer checks the citation dialog. Each section links to the handbook page carrying the detail and the sources.
1. How teams plan activities
The first question is who commits to a task. The lecture calls the two answers pull and push.
In Scrum the team pulls. Sprint planning starts from the hours the team really has; stories are broken into tasks, estimated, and taken only if they fit. During the sprint nobody assigns work: each person takes the next task at the daily scrum. The team commits “at the last responsible moment—the sprint planning for that sprint” [1]. For example, a team averaging 40 points plans about 20 for a sprint with two public holidays.
In a plan-driven project the manager pushes: “Every task that is scheduled should be assigned to a specific team member.” Its companion is effort validation, so that nobody is double-booked [2]. The detail is still planned late, one wave at a time, close to when each milestone’s work starts [3], [4].
Pull buys autonomy, and its typical failure is that nobody takes the awkward task. Push buys accountability, and its failure is a plan that outruns what people can do. A team can mix them, but everyone should know which one runs and who answers when a task is late.
2. Networks and the critical path
An activity network records which task waits for which, and nothing else: “Considerations of available manpower and equipment are conspicuous by their absence” [5]. Brooks warns that “The first chart is always terrible” [6]; draw it anyway, because drawing it forces every dependency into the open.
Each link has a type and a reason. Finish-to-start is the safe default: tuning starts when the PDF engine is in. Start-to-start, finish-to-finish and the rare start-to-finish buy time at the price of rework risk [7]. A technical dependency cannot be argued away; a management one can. Start with finish-to-start everywhere and relax a link only when the date demands it.
The critical path is “the sequence of activities that must be completed on schedule in order for the project to be completed on schedule” [7]. In Quill it is Ana’s stream and the acceptance run, nine weeks. These tasks have zero float: a week lost on the PDF engine is a week lost on go-live.
A manager does three things with it. Spend money only on critical tasks: speeding up Dana’s styles buys nothing. Recheck the path after every change, because it moves. And watch the nearly critical paths: Ivan’s stream is one week short. On DuPont’s first test, a chemical plant with 393 jobs, only about one job in ten was critical [5]. Without the network you expedite everything; with it you pay only for what moves the date. Two passes over the network give each task a window, earliest start to latest finish; the window minus the work is its float.
→ Activity planning · Critical path and float
3. Float and levelling
Float comes in two kinds that belong to different people [7]. Free float is how far a task can slip without delaying any successor: it belongs to the task owner. Total float is how far it can slip without delaying the project’s finish: it belongs to the path, and the first task to spend it takes it from the ones after.
Dana’s citation styles and the accessibility review both have four weeks of total float. But the review starts the moment the styles end, so every week Dana takes comes out of the reviewer’s four. The styles have no free float; the review’s four weeks are its own. Before you tell someone they have float, say which kind.
The network has no people in it, so the plan may need more people than exist. Levelling moves work to fit them, in a fixed order: spend free float, then total float; when float runs out, move the finish date; use overtime last [8], [7]. For example, the publisher asks for a two-week citation-engine fix that only Dana can make. Levelled, the fix goes first and her styles move later, spending two weeks of their float; go-live holds. Often there is no float: “It should be obvious to you that resource leveling almost always stretches the schedule” [7]. The network date is what the logic allows; the levelled date is what the team can deliver.
→ Critical path and float · Resource planning
4. Views of a plan
One plan has several drawings, and each answers one question.
A Gantt chart shows when: tasks as bars on a calendar, milestones as diamonds [2]. Anyone reads it in seconds, so it belongs in a status meeting. But “you cannot tell from the Gantt chart what must come before and after what” [7], and it shows who is assigned, not whether they are free. Report with the Gantt chart; decide with the network.
A network cannot draw a loop, and design work loops. A Design Structure Matrix (DSM) lists the tasks as both rows and columns; in Browning’s convention, “Subdiagonal elements indicate feedback—the potential for iteration and rework in the process” [9]. In Quill’s typesetting design, pagination and footnotes need each other: a citation reading see page 12 needs the page break, and long footnotes move it. Steward’s original matrix is the transpose [10], so check the convention first.
To handle a loop, partition the matrix so the coupled tasks form blocks, then tear each block by guessing the least risky missing input, and review the guess at the end [9]. Quill estimates the footnote space per page, paginates on that guess, and checks it after the citations are laid out. The sorted, torn matrix is an ordinary network.
| View | Answers | For |
|---|---|---|
| Milestone chart | What must be true, and by when | Sponsor |
| Gantt chart | What runs when, by whom | Team |
| Network | Which slip moves the date | Planner |
| DSM | Where work loops back | Design lead |
→ Gantt charts · Design Structure Matrix
5. Why schedules run late
The critical-path calculation assumes known durations, free people, no loops and kept safety. Real projects break all four, so the computed finish is a floor, never the forecast.
The most likely date is not a likely date. Durations are skewed: “while you can do only a limited number of things to shorten the duration of a task, the number of things that can go wrong is almost unlimited” [11]. A task with a best case of 10 days, a most likely 20 and a worst 40 has under a 40% chance of finishing by day 20. Ask for a range, as PERT’s three estimates do [12], and commit at a stated confidence.
Where paths merge, delays pass on. A merge point waits for the latest path, so the real finish is always later on average than the calculated one [13]. The merged path “passes on delays but seldom passes on savings” [11]. That is why Ivan’s stream is tracked as closely as Ana’s.
Best guesses run short, even with a record. Students forecasting their honours theses guessed 33.9 days and took 55.5; even their worst case was short half the time. “It seems that people can know the past and yet still be doomed to repeat it” [14]. Start from how long similar work took, and ask someone who is not the doer.
Safety gets spent. “It is a commonplace observation that work expands so as to fill the time available for its completion” opens Parkinson’s 1955 satire about officials; project management borrowed only that line [15]. Student syndrome, “leaving everything to the last minute”, is Goldratt’s term from a novel, with no study behind it, as Rand’s review reports [16]; Herroelen and Leus later tested the method built on it [17]. Buehler and colleagues measured the deadline effect: a one-hour task took 4.3 days on average with a week’s deadline and 9.1 with two [14]. Keep safety out of task deadlines.
Juggling makes everything late. In Zultner’s example, three projects share three people; switching project after every task makes all three finish late, while one at a time finishes each earlier [18]. Finish before you switch, and start fewer things.
→ PERT and merge bias · Critical chain
6. Critical chain
Goldratt’s diagnosis, in Rand’s summary, is that safety is added and then wasted: estimates are padded, work starts late, people are pulled away, and early finishes go unreported [16]. His remedy, critical chain project management, takes the safety out of each task and puts it where the date needs it; Herroelen and Leus tested its rules in simulation [17].
What survives is pooling: tasks rarely all go badly at once, so one shared buffer protects the date in less time than a pad on every task. Tasks are planned at 50/50 estimates, so half will overrun, and that must be acceptable: “The only way you will get accurate 50% likely expected task times is if it is OK to exceed them” [18].
The critical chain is the longest path once shared people are counted, a “leveled critical path” [19]. For example, before a Quill release build, Ana’s PDF export is the longest path by dependencies alone. But Dana has a fix and her citation styles, and in sequence they take longer. The manager watches Dana’s queue, not Ana’s progress.
Three buffers guard the chain: a project buffer at the end, a feeding buffer where a side path joins, and resource buffers that warn the next person to be ready. There are no task dates; the manager watches the project buffer instead. Leach’s rule reads it in thirds: do nothing, plan a response, act [20]. Raz and colleagues warn that the “days remaining” reports behind it can carry the same inflated safety the method set out to remove [19].
Both methods share the same risks: merge bias, biased estimates, heuristic levelling, political pressure, and tasks that run late together because they share a cause. A buffer manages the uncertainty that is left; risk management still has to remove the causes.
The evidence says keep the buffers, drop the arithmetic. In Herroelen and Leus’s simulation, sizing the project buffer at half the chain asked for 65% of the planned schedule, measured before execution, against 42% when sized from the tasks’ risk [17]. And estimates are not uniformly padded: in one IS department of over 500 tasks, 60% finished early, 8% on the estimate and 32% late [19]. Size buffers from risk, re-plan when the chain changes, and cut estimates from your own record, not by half.
Exam tip: the critical-chain evidence is thin. Of 140 papers, 8% are empirical, and no comparative study shows adopters perform better [21], [19]. Argue for the buffer, not for the method’s claimed savings.
→ Critical chain · Resource planning
Practice questions
1. Why say which kind of float a developer has before granting it?
Answer
Free float belongs to the task: spending it delays nobody. Total float is shared along the path, so spending it may take a colleague’s margin [7].
2. Why is the computed critical-path date a floor and not a forecast?
Answer
Durations are skewed late, merge points pass on delays but not savings, levelling stretches the plan, and safety gets spent [13], [11].
3. What from critical chain would you keep, and what would you drop?
Answer
Keep one visible, pooled buffer and watch it instead of single tasks. Drop the fixed rules: size buffers from risk and re-plan when the chain moves [17].
Where this goes next
Buffers protect a date. In release planning the date is fixed, so something else has to give: the scope. The next lecture applies the buffer idea to features instead of days.
Acknowledgments
This content is adapted from lectures by Eduardo Miranda [22] on software project management. The two-level view of planning, the three-buffer figure and the risks shared by critical path and critical chain are his.
References
- K. S. Rubin,Essential Scrum: A Practical Guide to the Most Popular Agile Process. in Addison-Wesley Signature Series (Cohn). Addison-Wesley Professional, 2012. [Online]. Available: https://innolution.com/essential-scrum
- R. S. Pressman,Software Engineering: A Practitioner’s Approach, 7th ed. McGraw-Hill, 2010.
- E. S. Andersen,“Warning: activity planning is hazardous to your project’s health!,” International Journal of Project Management, vol. 14, no. 2, pp. 89–94, Apr. 1996, doi: 10.1016/0263-7863(95)00056-9.
- G. D. Githens,“Rolling Wave Project Planning,” in Proceedings of the 29th Annual Project Management Institute 1998 Seminars & Symposium, Project Management Institute, Oct. 1998. [Online]. Available: https://www.wcu.edu/pmi/1998/NP02.PDF
- J. E. Kelley Jr. and M. R. Walker,“Critical-Path Planning and Scheduling,” in Papers Presented at the December 1–3, 1959, Eastern Joint IRE-AIEE-ACM Computer Conference, ACM, 1959, pp. 160–173. doi: 10.1145/1460299.1460318.
- F. P. Brooks,The mythical man-month (anniversary ed.). Addison-Wesley Longman Publishing Co., Inc., 1995.
- R. K. Wysocki and R. McGary,Effective Project Management: Traditional, Adaptive, Extreme, 3rd ed. Wiley Publishing, 2003.
- T. R. Browning,“Applying the Design Structure Matrix to System Decomposition and Integration Problems: A Review and New Directions,” IEEE Transactions on Engineering Management, vol. 48, no. 3, pp. 292–306, 2001, doi: 10.1109/17.946528.
- D. V. Steward,“The Design Structure System: A Method for Managing the Design of Complex Systems,” IEEE Transactions on Engineering Management, vol. EM-28, no. 3, pp. 71–74, 1981, doi: 10.1109/TEM.1981.6448589.
- E. Miranda,“Planning and executing time-bound projects,” Computer, vol. 35, no. 3, pp. 73–79, Mar. 2002, doi: 10.1109/2.989933.
- D. G. Malcolm, J. H. Roseboom, C. E. Clark, and W. Fazar,“Application of a Technique for Research and Development Program Evaluation,” Operations Research, vol. 7, no. 5, pp. 646–669, 1959, doi: 10.1287/opre.7.5.646.
- K. R. MacCrimmon and C. A. Ryavec,“An Analytical Study of the PERT Assumptions,” Operations Research, vol. 12, no. 1, pp. 16–37, 1964, doi: 10.1287/opre.12.1.16.
- R. Buehler, D. Griffin, and M. Ross,“Exploring the ‘Planning Fallacy’: Why People Underestimate Their Task Completion Times,” Journal of Personality and Social Psychology, vol. 67, no. 3, pp. 366–381, 1994, doi: 10.1037/0022-3514.67.3.366.
- C. N. Parkinson,“Parkinson’s Law,” The Economist, Nov. 1955, [Online]. Available: https://www.economist.com/news/1955/11/19/parkinsons-law
- G. K. Rand,“Critical chain: the theory of constraints applied to project management,” International Journal of Project Management, vol. 18, no. 3, pp. 173–177, June 2000, doi: 10.1016/S0263-7863(99)00019-8.
- W. Herroelen and R. Leus,“On the Merits and Pitfalls of Critical Chain Scheduling,” Journal of Operations Management, vol. 19, no. 5, pp. 559–577, 2001, doi: 10.1016/S0272-6963(01)00054-7.
- B. Lynch,“Critical Chain Project Management: Coming to a Radar Screen Near You!,” Cutter IT Journal, vol. 16, no. 3, Mar. 2003.
- T. Raz, R. Barnes, and D. Dvir,“A Critical Look at Critical Chain Project Management,” Project Management Journal, vol. 34, no. 4, pp. 24–32, 2003, doi: 10.1177/875697280303400404.
- L. P. Leach,“Critical Chain Project Management Improves Project Performance,” Project Management Journal, vol. 30, no. 2, pp. 39–51, 1999, doi: 10.1177/875697289903000207.
- M. Ghaffari and M. W. Emsley,“Current status and future potential of the research on Critical Chain Project Management,” Surveys in Operations Research and Management Science, vol. 20, no. 2, pp. 43–54, Dec. 2015, doi: 10.1016/j.sorms.2015.10.001.
- E. Miranda,“Managing Software Development.” 2014.