SN L6a — Release Planning
A revision summary of the release-planning lecture. Release planning decides which features go into which release when the date is fixed and the backlog is longer than the time. The lecture follows Quill 1.0, the invented word processor from the requirements and risk lectures: six people, a publisher as the customer, a release due on 1 February that will not move, and a backlog (open and save, a spell checker, track changes, comments, autosave, mail merge, a grammar checker…) longer than six people can build by then. Two questions run through all six parts: what can you promise for the date, and what can you only hope for? And when something goes wrong, what gives, and who decides? Each section links to the handbook page carrying the detail and the sources.
1. Releases and iterations
The date holds; the scope moves. The release date is fixed, or may be; its content is not, at least not at first. The sponsor may get less than they would like, and the two sides choose together what to protect and what to give up. Rubin: “the variables of date and scope are constantly playing a game of chicken with each other!” [1]. In release planning you decide in advance that the scope swerves. This is not only agile: Miranda calls such projects time-bound, where the timing of the delivery matters as much as the delivery [2].
A release ends in useful software, for the customer; an iteration (sprint) ends in working software, for the team. Release planning decides which features go in which release; iteration planning decides how this batch gets built. Typical lengths are three to nine months for a release and one week to one month for a sprint [1]. For example, after Quill’s first sprint open and save works and the team can demo it, but the publisher’s editors cannot work in a word processor that only opens and saves.
How often to release is a business decision. Every sprint ends potentially shippable; shipping it is the business’s choice. One e-store was delivered after 6 weeks and then every 3 weeks, with several time boxes running at once [3]. Is an iteration a release? Ask who receives it.
A fixed-date plan answers how much? with a range: will have, might have, won’t have. Keep the must-haves at 60–70% of the time, so something can still give [1]. “The end-date for the timebox is not a due date. It’s a deadline.” [4]
Release planning assigns features to a sequence of releases, balancing business objectives, technical dependencies, resource limits and stakeholders who are not equally important [5]. Commit to the next release; sketch the ones after it, and re-plan after each delivery [6]. Pick a strategy before picking features: a single release, or incremental ones ordered by threshold of success, themes, risk or return on investment [7]. A backlog still needs a reason for its order.
Releasing early also changes when the money comes back. In Denne and Cleland-Huang’s example, a year of development has a net present value of −$24K as one release and +$205K as four quarterly ones: with one release, “the business is drained of value if it undertakes the project, despite the positive ROI.” [8]
2. Choosing what goes in
Release planning is a knapsack with dependencies: each feature has a value and a cost, each release a capacity, and features depend on each other. Values are far from equal: in one Ericsson project the top requirement was worth about twenty times the least. In Karlsson and Ryan’s cost–value approach, customers compare requirements in pairs by value and engineers by cost; dropping 3 of 14 requirements kept 94% of the value at 78% of the cost. The price is n(n−1)/2 comparisons, and dependencies are ignored [9].
Each method optimises a different goal: MoSCoW a guaranteed minimum plus contingency, cost–value value per unit of cost, EVOLVE stakeholder urgency against business value [6], the Incremental Funding Method net present value, Buffered MoSCoW and SPID delivery certainty by a fixed date. The computer proposes; a person chooses. Name the factors your situation needs, then pick the cheapest method that covers them [10].
MoSCoW, coined by Clegg and Barker [11], has four categories, which DSDM defines by consequence, not importance [12]. A Must is the “Minimum Usable SubseT” the project guarantees. A Should is important but not vital: a painful workaround exists. A Could is “the main pool of contingency”. A Won’t is agreed not to be delivered this time. For Quill: open and save is a Must, autosave a Should (you can save by hand), the grammar checker a Could, mail merge a Won’t. The test for a Must: “if I come to you the night before Deployment and tell you there is a problem with a Must Have requirement and that we can’t deliver it – will you stop the Deployment?”
DSDM gives Musts “no more than 60%” of the effort and Coulds “around 20%”, and no figure for the Shoulds: the “60/20/20” you meet in industry infers the middle number. More than 60% is acceptable only when estimates are accurate, the approach known, the team performing and the risks low [12].
3. Buffered MoSCoW
Why 60%? Miranda simulated DSDM’s rule: with Musts at 60% of the budget and every feature overrunning by up to double its estimate, all Musts were delivered about 99% of the time; at 70%, about a third of the time. It holds when each category has at least five features and none takes more than a quarter of it [13]. Split big features.
Buffered MoSCoW asks how likely, not how important [14]. A Must is delivered “short of a calamity”; a Should has “a fair chance of being delivered”; a Could arrives only “if everything went extraordinarily well”; a Won’t has no budget left at its safe estimate. The customer still ranks; the estimates decide how far down the ranking the time box can promise.
Each feature gets a normal estimate, with a fair chance of being enough, and a safe one, enough except in a few really bad cases: Quill’s spell checker might take two weeks normally and four safely. Then the rule:
- The customer ranks the features; the team gives each a normal and a safe estimate.
- Musts: in rank order, with their prerequisites, at their safe estimates, until the development budget is used. Re-plan them at normal; the time freed is the Must buffer.
- Shoulds: in the customer’s order, at their safe estimates, inside the Must buffer; re-planned at normal, they free the Should buffer. Coulds go inside the Should buffer.
- What fits nowhere at its safe estimate is a Won’t.
Miranda: “We will repeat the process for the ‘should have’ and ‘could have’ requirements using the size of the buffer protecting the previous category as the initial budget for the current one” [14]. Every category is planned at its safe estimate; what differs is whose overruns it absorbs.
There are no fixed percentages. Wide gaps between safe and normal give a small Must set and big buffers; narrow gaps the opposite. A Should ships only if the Musts come in at or under normal, roughly half the time; a Could needs the Musts and the Shoulds to. So the relative odds are Must 4 · Should 2 · Could 1. Tell the sponsor exactly that.
Exam tip: the common mistake is “the Shoulds take whatever is left, at normal”. They are chosen in the customer’s order, at their safe estimates, inside the Must buffer.
4. Running the time box
A Must overrun costs the Could, not the date. If Quill’s spell checker takes its safe estimate, the overrun eats the Must buffer and every Must still ships; the Should keeps a fair chance; the Could becomes unlikely [14]. Nobody renegotiates: the plan said on day one what would go first.
A change waits for the next sprint and costs scope. When? At the next iteration boundary; the running sprint is frozen. Who? The customer decides on value; the team advises on cost and risk [15]. What gives? The lowest-priority scope; growth in the Musts goes to the sponsor [12]. After a demo, Quill’s publisher moves comments above mail merge. At the next sprint planning comments comes in, mail merge drops below the line, and 1 February stays. Moving the date is a separate decision, by the sponsor, taken last.
Infrastructure is a feature the others depend on. Split it into the part each release strictly needs: Quill’s PDF engine comes in with export and print preview [7]. Defects follow the same logic: critical and major ones are fixed in the time box where they are found, minor ones later, and the customer chooses between fixes and new features [14].
The commitment can be made once for the project or once per increment. Per increment means smaller promises, kept more often; a Could missed in release 1 can become a Must for release 2 [12].
5. Contracts and incentives
An honest plan promises only the Musts. The risk of partial delivery does not go away; the only choice is who carries it. Under a fixed price the supplier does, and charges a premium, cuts quality or fights later. Under time and materials the buyer does, with no limit on cost. An incentive contract splits it: a base for the Musts, premiums for the Should and Could releases. “the incentives and disincentives will prevent the developer from charging a premium price to protect itself from not delivering all features” [13].
Price the contract on its odds, not its best case. For example, a 4,000-hour time box at $100 an hour costs $400K; a fixed price of $520K is a 30% markup. Paid on delivery, the client pays $400K for the Musts only, $500K with the Shoulds and $550K for everything. At odds of one half, one quarter and one quarter, the expected price is about $462.5K [7]. The supplier sets the base and premiums on that, or knowingly accepts less money for a lower-risk deal.
Inside the team: “No reward will be associated with delivering the ‘must have’ release since the team members are simply doing their jobs.” [14] Bonuses go to the Should and Could releases, sized by expected value: $5,000 at even odds is worth about $2,400. A big reward nobody believes in is a lottery [2]. Tie bonuses to release completion, not overtime; training and time off count too.
Unused buffer gets spent unless handing it on pays. “work expands so as to fill the time available for its completion” [16], and the student syndrome starts work only when the deadline comes into view: given the same one-hour task, students finished at 4.3 days with a one-week deadline and 9.1 with two [17]. In Buffered MoSCoW, time a Must does not use belongs to the next feature the customer wanted. Miranda names these behaviours only to explain why effort runs late [13]; tying them to rewards is the lecture’s own step. Reward the Should and Could releases, and the team has a reason to hand the buffer on.
6. When two estimates are not enough
Independent overruns partly cancel. A shared cause does not: an immature open-source library slows the testing and debugging of every feature that uses it, so they overrun together. With low-confidence estimates and overruns that move together, all Musts were delivered only about three times in four [13]. Keep features small and independent.
When the sponsor needs a stated probability, use SPID, Statistically Planned Incremental Deliveries: three-point estimates, the first increment filled to about 95% confidence, re-planned at 50%, and the difference handed to the next increment [2]. Buffered MoSCoW is its simple version. For “short of a calamity”, two estimates are enough; for “95% sure”, model it.
Exam tip: these methods are well argued and thinly measured. Buffered MoSCoW comes from a five-page essay, the 4 : 2 : 1 odds are argued, and the 60% simulation covers estimation error, not scope change. Quote them as reasoning, never as industry rates.
Where this goes next
Quill now has a plan with buffers in it. The next question is how to see, week by week, whether the buffer is being used up faster than the work is getting done: monitoring and control.
Acknowledgments
This content is heavily inspired by and adapted from lectures by Eduardo Miranda [7] on software project management. Buffered MoSCoW, SPID, the release strategies, the incentive contract and its pricing example are Miranda’s.
References
- K. S. Rubin,Essential Scrum: A Practical Guide to the Most Popular Agile Process. in Addison-Wesley Signature Series (Cohn). Addison-Wesley Professional, 2012. [Online]. Available: https://innolution.com/essential-scrum
- E. Miranda,“Planning and executing time-bound projects,” Computer, vol. 35, no. 3, pp. 73–79, Mar. 2002, doi: 10.1109/2.989933.
- P. Jalote, A. Palit, P. Kurien, and V. T. Peethamber,“Timeboxing: A Process Model for Iterative Software Development,” Journal of Systems and Software, vol. 70, no. 1–2, pp. 117–127, 2004, doi: 10.1016/S0164-1212(03)00010-4.
- S. McConnell,Rapid development: taming wild software schedules. Pearson Education, 1996.
- G. Ruhe and M. O. Saliu,“The Art and Science of Software Release Planning,” IEEE Software, vol. 22, no. 6, pp. 47–53, 2005, doi: 10.1109/MS.2005.164.
- D. Greer and G. Ruhe,“Software release planning: an evolutionary and iterative approach,” Information and Software Technology, vol. 46, no. 4, pp. 243–253, Mar. 2004, doi: 10.1016/j.infsof.2003.07.002.
- E. Miranda,“Managing Software Development.” 2014.
- M. Denne and J. Cleland-Huang,“The incremental funding method: data-driven software development,” IEEE Software, vol. 21, no. 3, pp. 39–47, May 2004, doi: 10.1109/MS.2004.1293071.
- J. Karlsson and K. Ryan,“A Cost-Value Approach for Prioritizing Requirements,” IEEE Software, vol. 14, no. 5, pp. 67–74, 1997, doi: 10.1109/52.605933.
- M. Svahnberg, T. Gorschek, R. Feldt, R. Torkar, S. B. Saleem, and M. U. Shafique,“A Systematic Review on Strategic Release Planning Models,” Information and Software Technology, vol. 52, no. 3, pp. 237–248, 2010, doi: 10.1016/j.infsof.2009.11.006.
- D. Clegg and R. Barker,Case Method Fast-Track: A Rad Approach. Addison-Wesley Longman Publishing Co., Inc., 1994.
- DSDM Consortium,The DSDM Agile Project Framework. Dynamic Systems Development Method Limited, 2014. [Online]. Available: https://www.agilebusiness.org/wp-content/uploads/2026/05/DSDM-Agile-Project-Framework-Handbook.pdf
- E. Miranda,“Moscow Rules: A Quantitative Exposé,” in Agile Processes in Software Engineering and Extreme Programming (XP 2022), in Lecture Notes in Business Information Processing. Springer, 2022, pp. 19–34. doi: 10.1007/978-3-031-08169-9_2.
- E. Miranda,“Time boxing planning: buffered moscow rules,” ACM SIGSOFT Software Engineering Notes, vol. 36, no. 6, pp. 1–5, Nov. 2011, doi: 10.1145/2047414.2047428.
- Z. Racheva, M. Daneva, A. Herrmann, and R. J. Wieringa,“A Conceptual Model and Process for Client-Driven Agile Requirements Prioritization,” in Fourth International Conference on Research Challenges in Information Science (RCIS), IEEE, 2010, pp. 287–298. doi: 10.1109/RCIS.2010.5507388.
- C. N. Parkinson,“Parkinson’s Law,” The Economist, Nov. 1955, [Online]. Available: https://www.economist.com/news/1955/11/19/parkinsons-law
- R. Buehler, D. Griffin, and M. Ross,“Exploring the ‘Planning Fallacy’: Why People Underestimate Their Task Completion Times,” Journal of Personality and Social Psychology, vol. 67, no. 3, pp. 366–381, 1994, doi: 10.1037/0022-3514.67.3.366.