SN L6b — Tracking, Reporting and Controlling

A revision summary of the tracking lecture. Tracking finds out where the project really is; reporting tells the people who depend on it, at fixed intervals; controlling does something about what the report shows. The lecture returns to Quill 1.0, the invented word processor from the earlier lectures, nine weeks before its 1 February release: six people, a publisher as the customer, and a critical path through the new PDF engine, tuning for 500-page documents and the acceptance run. Quill is invented, and every number about it is an example. The publisher asks whether Quill is on track, and the team answers “about 90%”: no unit, no evidence, no decision. Each section links to the handbook page carrying the detail and the sources.

1. Measuring progress

Progress is a curve, not a straight line. Output rises, peaks and tails off, so a straight line drawn through the first weeks promises a date the project will not keep. The 90% syndrome is a project that reaches about 90% on schedule, then stalls and finishes at about twice the planned duration [1]. Ford and Sterman’s Python project, a chip design rather than software, was 73% complete at its week-39 deadline; its rate then halved, and it finished in week 69.

The first cause is rework nobody has found yet. Python counted lines of design code, an objective count, and still stalled. Work was marked done, its errors surfaced later in testing, and everything built on it went round again: “the downstream phases outrun the discovery of inherited rework requirements.” For example, Quill’s Ana has reported her 500-page performance prototype at 90% for three weeks, because every larger test document shows more to tune. Nobody is lying. Optimistic reporting is the second cause: it keeps the stall hidden. So put rework in the plan, and test and integrate early.

Done has to mean done. Brooks wants milestones “defined with knife-edge sharpness” [2]; McConnell makes them binary, done or not done [3]. A milestone trend chart plots every milestone’s forecast date at each report, so a small slip repeated every week shows as a slope rather than a surprise. Quill’s milestone B, the 500-page result, moved from 18 to 26 January over the last four reports; four slips in a row is a signal to act [4].

Calculate percent complete; never ask for it. Count finished tasks over all tasks, or running, tested features over all features, with work under way counting zero [4]. Asked for a percentage, a person’s first thought is “What percent should I be?” For Quill, count the 1.0 features that run and pass their tests, and divide by all of them: the publisher can recount that herself.

→ Reporting progress

2. Getting the bad news

Good news finds you; bad news has to be fetched. “positive information is likely to flow up organizational hierarchies much more readily than negative information” [5]. In Keil’s experiment, willingness to report fell at each step up the hierarchy, and further where messengers had been punished [6].

Silence is the default. 85% of Milliken’s interviewees had held back an important issue, most often someone’s competence, mostly for fear of being labelled a troublemaker [5]. That is the topic behind many a task stuck at 90% on the board: a colleague who is struggling. A quarter thought speaking up was futile.

Ask to see it, then act. The manager walks around, often and unannounced, and asks “can you show me?” Asking Ana to open a 500-page document in front of you turns a percentage into done or not done. Then act on what you hear, or say why not: people stop telling a manager who does nothing. But keep the status meeting separate from the problem-solving one, or every report becomes an intervention [2].

→ Reporting progress

3. Earned value

Earned value is the budget of the work actually finished. It uses three numbers, in money or in person-hours. Planned value (PV) is the budget of the work scheduled by now, earned value (EV) the budget of the work finished by now, and actual cost (AC) what the finished work cost [7]. SPI = EV / PV reads schedule; CPI = EV / AC reads cost; below 1.0 is worse than plan. A task planned at 10 hours that took 14 earns 10.

Spending on plan says nothing about progress. PV and AC are both spending curves, so comparing them is “an indicator only of spending and not of overall project performance” [8]. In the lecture’s eight-week example, at week 4 the plan called for 16 hours of work, the finished tasks were budgeted at 12, and the team had spent 18. Against PV alone, the spend looks a little over plan; EV shows the project behind and over.

Value is earned by a rule fixed before work starts. Under 0/100 a task earns its budget only when finished; under 50/50, half at the start and half at the finish. Neither can be talked up. Self-reported percent complete can, and it carries the 90% syndrome straight into the curve. But 0/100 removes the optimism, not the rework: an honestly finished task can still come back. And keep the baseline still: “Lack of baseline control can doom a project.” [7]

Read the two indices together, and forward. Behind schedule and under budget is a cost warning, not a saving: “because schedule problems are often resolved by additional spending, an adverse SPI is also predictive of later cost problems” [9]. In one project Lipke charts, CPI stayed above 1.1 for four months while SPI sat near 0.8, then fell below 1 and finished near 0.7 [10]. An SPI above 1 can mislead too, if the extra work is off the critical path: check the float [11]. Act early, because cumulative CPI settles by about 20% complete [9].

A late project ends with a perfect SPI. SPI is measured in money. When a late project finishes, all its planned value has been earned, so SPI returns to 1.0 whatever the delay; the schedule indices say little in the final third [10]. Earned schedule reads the gap in months instead: when did the plan expect today’s earned value?

→ Earned value

4. Reading agile charts

Two burndowns answer two questions. The sprint burndown holds hours of task work left, updated daily, and belongs to the team: will we finish this sprint? The release burndown holds story points left, updated once per sprint, and belongs to the product owner and stakeholders: when is the release done, and with what? [12] A sprint line that goes up is usually an estimate getting better: in Rubin’s example, remaining work rose from 180 to 190 hours because one task was re-estimated from 8 to 16.

A flat release burndown has two causes. Remaining work is total scope minus work done, and both terms move. Slow work flattens the line; so does scope added as fast as the team finishes it. They need opposite responses: a slow team needs its impediment found, while growing scope is the product owner’s call, to cut scope or move the date. The burn-up draws work done and total scope as separate lines, so it tells the two apart. On a Slovenian newspaper site, the team completed about 155 points in six sprints while remaining work fell only from about 64 to about 52, because the product owner kept adding requirements; the company shipped a reduced release after 9 sprints [13]. When the publisher moved comments into Quill 1.0, Quill’s burndown flattened too, and the burn-up shows the team still delivering. Before you push the team, check whether the target moved.

→ Burndown and burn-up charts

Velocity forecasts until it becomes a target. Velocity is the size of the items finished in a sprint; partly done counts zero. Points left divided by velocity gives a range: 200 points at 17 to 20 a sprint is 10 to 12 sprints, not 10 [12]. Re-forecast every sprint. As a target, it stops measuring the work. At ThoughtWorks, managers “excused the developers from writ[ing] tests, and the testers cut on the thoroughness of the testing in hopes to maintain the velocity” [14].

Flow shows where work waits. In a cumulative flow diagram, a widening middle band means work started and waiting. It suits maintenance and support, where there is no release to burn down; BBC Worldwide cut lead time by 37% after starting fewer features at once [15].

→ Velocity and flow

5. Choosing and controlling

Only earned value sees the money. On a Scrum project, SPI is the burndown’s gap written as a ratio, and both forecast the same release date: on two projects the dates were “indistinguishable” [16]. What earned value adds is CPI: a burndown never holds effort spent, so it cannot show cost. Project A, “a one-half million dollar web application project” run in Scrum, burned points at the planned rate, yet “the CPI index clearly shows the erosion of this buffer that the burndown doesn’t recognize.” So the deciding question is not agile or plan-driven but who owns a budget. Quill’s publisher bought it on an incentive contract in the release-planning lecture, so she gets earned value at release level, and the team keeps its burndown.

→ Choosing a tracking instrument

Decide in advance which variance gets action. A magnitude line catches a large gap: Wysocki treats a 10% cost variance as “the most allowed” [4]. A trend line, such as Quill’s four slips in a row, fires earlier. Crossing a line starts an analysis, not an action: “the conditions must be analyzed to identify why the variance exists” [8].

Every corrective action spends something. Overtime gives a short gain, then “an aggressive decline in velocity along with a simultaneous decline in quality” [12]: it buys a week now and rework later. Adding people has the same shape [2]. Wysocki’s ladder orders the alternatives by who pays, cheapest first: leave a slip alone if the task has float, overlap tasks, reassign people from non-critical work, ask resource managers for more, offer the customer the key features on the date, and only last ask for more time, which “offers the customer nothing in trade.” [4] Quill’s B has no float, but E, Dana’s citation styles, has four weeks of it, so effort moves from E to B before anyone asks the publisher.

Predictive control holds scope fixed and steers cost and schedule back to the baseline; agile control holds the time box fixed and steers scope.

Stopping is the hardest action. CONFIG, an expert system, was funded for more than a decade while its usage fell from about 2.3% of quotations to about 0.1% [17]. A sales rep said “The problem is nobody is willing to kill it.” That is escalation of commitment. Write a stop rule on what the project is for, before anyone is attached: escalate the problem early, so nobody escalates the commitment later.

→ Controlling a project

6. Reporting: answer first

A Red project is often reported Green. Status error has two parts, not knowing and not saying [18]. Under moderate good-news bias, their model has a truly Red high-risk project reach the executive as Green about half the time, and halving the perception error barely changes that. Distortion is “likely to be significantly higher in organizations where ‘bad news gets you killed.’” The reader of the reports owns the climate.

Red is a request for help, not a confession. Print what the colours mean: Yellow comes with a get-well plan, Red has none and asks for help [4]. Ask for one light per dimension, cost, schedule and function, because one overall colour is easy to round up [18]. Across many projects, count the colours and show the worst; traffic lights are ordinal, so never average them [19].

Open the report with its colour and the decision. A status report asks its reader to decide, so it takes the Minto pyramid: answer, then reasons, then evidence [20]. The usual template opens with the period’s chronicle and puts the decision in its last line. Reordered, with nothing added and nothing cut, Quill’s report opens:

Schedule Yellow: B, the 500-page work, has slipped at four reports and has no float. We are moving effort to B to hold 1 February. If B slips again, we need your agreement that the grammar checker moves to 1.1. Cost and function Green.

The three lights follow, then the evidence, with the period’s chronicle last. The grammar checker is a Could in Quill’s release plan, so dropping it is the release plan working. The shape gets the bad news read; the climate gets it written.

→ Reporting progress

Where this goes next

The tracking case applies these instruments to a project of its own, with the earned-value arithmetic and the burndown reading this lecture left out.


Acknowledgments

This content is heavily inspired by and adapted from lectures by Eduardo Miranda and David Root [21], [22] on software project management. The earned-value worked example, the overtime loop, the milestone trend chart’s structure, the status-report template and the planning–tracking table are theirs.

References

  1. D. N. Ford and J. D. Sterman,
    “Overcoming the 90% Syndrome: Iteration Management in Concurrent Development Projects,” Concurrent Engineering: Research and Applications, vol. 11, no. 3, pp. 177–186, 2003, doi: 10.1177/106329303038031.
  2. F. P. Brooks,
    The mythical man-month (anniversary ed.). Addison-Wesley Longman Publishing Co., Inc., 1995.
  3. S. McConnell,
    Rapid development: taming wild software schedules. Pearson Education, 1996.
  4. R. K. Wysocki and R. McGary,
    Effective Project Management: Traditional, Adaptive, Extreme, 3rd ed. Wiley Publishing, 2003.
  5. F. J. Milliken, E. W. Morrison, and P. F. Hewlin,
    “An Exploratory Study of Employee Silence: Issues that Employees Don’t Communicate Upward and Why,” Journal of Management Studies, vol. 40, no. 6, pp. 1453–1476, 2003, doi: 10.1111/1467-6486.00387.
  6. M. Keil, H. J. Smith, S. Pawlowski, and L. Jin,
    “‘Why Didn’t Somebody Tell Me?’: Climate, Information Asymmetry, and Bad News about Troubled Projects,” ACM SIGMIS Database: the DATABASE for Advances in Information Systems, vol. 35, no. 2, pp. 65–84, 2004, doi: 10.1145/1007965.1007971.
  7. Humphreys & Associates,
    “Basic Concepts of Earned Value Management (EVM).” 2012. Accessed: Oct. 26, 2025. [Online]. Available: https://www.humphreys-assoc.com/basic-concepts-of-earned-value-management-evm/
  8. NASA,
    “NASA Systems Engineering Handbook,” National Aeronautics and Space Administration, NASA Special Publication SP-2007-6105 Rev1, Dec. 2007. [Online]. Available: https://www.nasa.gov/reference/systems-engineering-handbook/
  9. D. S. Christensen,
    “The Costs and Benefits of the Earned Value Management Process,” Journal of Parametrics, vol. 18, no. 2, pp. 1–16, 1998, doi: 10.1080/10157891.1998.10462568.
  10. W. Lipke,
    “Schedule Is Different,” The Measurable News, pp. 10–15, Mar. 2003, [Online]. Available: https://www.earnedschedule.com/Docs/Schedule%20is%20Different.pdf
  11. J. A. Lukas and P. Cce,
    “Earned Value Analysis - Why it Doesn’t Work,” 2008.
  12. K. S. Rubin,
    Essential Scrum: A Practical Guide to the Most Popular Agile Process. Addison-Wesley, 2012.
  13. V. Mahnič and N. Žabkar,
    “Measuring Progress of Scrum-based Software Projects,” Elektronika ir Elektrotechnika, vol. 18, no. 8, pp. 73–76, 2012, doi: 10.5755/j01.eee.18.8.2630.
  14. E. Kupiainen, M. V. Mäntylä, and J. Itkonen,
    “Using Metrics in Agile and Lean Software Development – A Systematic Literature Review of Industrial Studies,” Information and Software Technology, vol. 62, pp. 143–163, 2015, doi: 10.1016/j.infsof.2015.02.005.
  15. P. Middleton and D. Joyce,
    “Lean Software Management: BBC Worldwide Case Study,” IEEE Transactions on Engineering Management, vol. 59, no. 1, pp. 20–32, 2012, doi: 10.1109/TEM.2010.2081675.
  16. T. Sulaiman, B. Barton, and T. Blackburn,
    “AgileEVM – Earned Value Management in Scrum Projects,” in Proceedings of AGILE 2006 (AGILE’06), IEEE, 2006, pp. 7–16. doi: 10.1109/AGILE.2006.15.
  17. M. Keil,
    “Pulling the Plug: Software Project Management and the Problem of Project Escalation,” MIS Quarterly, vol. 19, no. 4, pp. 421–447, 1995, doi: 10.2307/249627.
  18. A. P. Snow and M. Keil,
    “The Challenge of Accurate Software Project Status Reporting: A Two-Stage Model Incorporating Status Errors and Reporting Bias,” IEEE Transactions on Engineering Management, vol. 49, no. 4, pp. 491–504, 2002, doi: 10.1109/TEM.2002.807290.
  19. S. S. Stevens,
    “On the Theory of Scales of Measurement,” Science, vol. 103, no. 2684, pp. 677–680, 1946, doi: 10.1126/science.103.2684.677.
  20. B. Minto,
    The Pyramid Principle: Logic in Writing and Thinking. Pearson Education, 2009.
  21. E. Miranda,
    “Managing Software Development.” 2014.
  22. D. Root,
    Managing Software Development. Carnegie Mellon University / Innopolis University lecture series, 2014.