Planning approaches

A plan is a set of documented agreements on what will be delivered, when, and by whom [1]. A planning approach decides when those agreements are made, who makes them, and which coordination mechanism carries them.

1. A plan is coordination prepared in advance

Coordination means “managing dependencies among tasks” [2]. Teams manage them in four ways, and every real team uses all four:

Mechanism Software example Its cost
Reference to a higher level the tech lead rules on an interface dispute one person becomes the bottleneck [3]
Preparation the release plan, the interface specification breaks on the uncertain parts of the work
Shared representations [3] the code, the task board, the CI dashboard someone must keep them current
Communication the stand-up, the design review suffers first when the team is split

A plan is the preparation row. Routine dependencies can be coordinated “mechanistically” through plans, schedules and specifications; surprises such as missed deadlines need coordination “organically”, through communication [4]. Distance damages talk before it damages a plan. In a two-site telecom team, two network elements “worked well individually, but not together because the specs were misinterpreted, which delayed the testing by six weeks” [4].

2. What a plan is for

A plan does not stop change. “Its purpose is to help assess and measure the impact of changes on previous commitments so that informed decisions can be made” [1]. When DuPont changed about 40% of a critical-path plan, re-planning took about 10% of the original effort [5].

Agile teams agree: Scrum teams “often spend more time planning with Scrum than with traditional development”, in smaller pieces and closer to the work [6]. The lecture adds an analogy: a good plan has the properties of a good program. Booking one developer on two tasks at once is a race condition; a circular dependency is a deadlock.

3. Predictive and agile plans decide the same things at different moments

Both approaches answer the same questions, at different times and by different people [1]:

Decision Predictive Agile (Scrum)
What deliverables? WBS, at the start product backlog, at the start and later
When delivered? milestone plan, at the start item priority; no firm date
What tasks? WBS, at the start and each planning wave sprint backlog, at sprint planning
When executed? network and Gantt chart; the manager assigns (push) when someone is free (pull)
Who does it? responsibility matrix task board, at the daily scrum

Push, in a standard text: “Every task that is scheduled should be assigned to a specific team member” [7]. Pull, in the Scrum Guide: “The Sprint Backlog is a plan by and for the Developers” [8]. Agile planning still has horizons: Rubin names five, from portfolio down to release (up to nine months), sprint (one week to one month) and the day [6].

Rubin's planning levels as nested circles, strategy outermost, then portfolio, product, release, sprint and daily; only the sprint and daily levels are defined by Scrum itself

Rubin 2012, Fig. 15.1; horizons from Table 15.1.

Which way to lean depends on how much will change before you get there. Stable requirements, large teams and safety-critical work favour a predictive plan; a product still being discovered by a small, skilled team favours agile planning. Boehm and Turner call these a method’s home ground [9].

4. Two plans, two readers

A sponsor-oriented plan lists results the sponsor can check, with dates. It is the milestone plan, “read and understood without having any detailed insight into the underlying activities” [10]. A developer-oriented plan lists iterations, phases, tasks and owners: the plan the team runs.

For example, Quill is a fictional word processor built for a publishing house. “Iteration 3 done” tells the publisher nothing she can check; “When the publisher has agreed the Quill 1.0 feature list” does. A changed task order is the team’s business. A changed result or date is a renegotiation with the sponsor.

The limitation applies to both plans. Up-front plans “very accurately encode our early ignorance” [6]: they cover only the dependencies someone foresaw, and talk must handle the rest.

How solid is this?

  • Where it comes from. One field study of one telecom team at two sites, 32 coded interviews, counting who mentioned a problem rather than how often it occurred [4]; and one eight-month study of one design project [3]. Herbsleb 2007 is a roadmap with no data of its own.
  • What we do not hold. Reference to a higher level is hierarchy in the classic organisational literature, which is not in this bibliography. Earlier versions credited the four-row table to a 2009 Herbsleb talk that could not be traced.
  • What is the lecture’s. The good-plan analogy and the term developer-oriented plan. The re-plan figure is the CPM inventors’ own report of one project; Rubin and Pressman are practitioner books, and the Scrum Guide is normative.

Acknowledgments

This page adapts material from lectures by Eduardo Miranda [1] on software project management.

References

  1. E. Miranda,
    “Managing Software Development.” 2014.
  2. J. D. Herbsleb,
    “Global Software Engineering: The Future of Socio-technical Coordination,” in Future of Software Engineering (FOSE ’07), May 2007, pp. 188–198. doi: 10.1109/FOSE.2007.11.
  3. J. D. Herbsleb, H. Klein, G. M. Olson, H. Brunner, J. S. Olson, and J. Harding,
    “Object-Oriented Analysis and Design in Software Project Teams,” Human–Computer Interaction, vol. 10, no. 2–3, pp. 249–292, 1995, doi: 10.1207/s15327051hci1002&3_4.
  4. J. A. Espinosa, S. A. Slaughter, R. E. Kraut, and J. D. Herbsleb,
    “Team Knowledge and Coordination in Geographically Distributed Software Development,” Journal of Management Information Systems, vol. 24, no. 1, pp. 135–169, 2007, doi: 10.2753/MIS0742-1222240104.
  5. J. E. Kelley Jr. and M. R. Walker,
    “Critical-Path Planning and Scheduling,” in Papers Presented at the December 1–3, 1959, Eastern Joint IRE-AIEE-ACM Computer Conference, ACM, 1959, pp. 160–173. doi: 10.1145/1460299.1460318.
  6. K. S. Rubin,
    Essential Scrum: A Practical Guide to the Most Popular Agile Process. in Addison-Wesley Signature Series (Cohn). Addison-Wesley Professional, 2012. [Online]. Available: https://innolution.com/essential-scrum
  7. R. S. Pressman,
    Software Engineering: A Practitioner’s Approach, 7th ed. McGraw-Hill, 2010.
  8. K. Schwaber and J. Sutherland,
    “The Scrum Guide.” Nov. 2020. [Online]. Available: https://scrumguides.org/docs/scrumguide/v2020/2020-Scrum-Guide-US.pdf
  9. B. Boehm and R. N. Turner,
    Balancing Agility and Discipline: A Guide for the Perplexed. Addison-Wesley Professional, 2003.
  10. E. S. Andersen,
    “Warning: activity planning is hazardous to your project’s health!,” International Journal of Project Management, vol. 14, no. 2, pp. 89–94, Apr. 1996, doi: 10.1016/0263-7863(95)00056-9.