Critical path and float
The critical path is “the sequence of activities that must be completed on schedule in order for the project to be completed on schedule” [1]. Float (or slack) is how far any other task can slip before it, too, moves a date that matters.
1. What it is
The method comes from DuPont and Remington Rand UNIVAC, developed in 1957 and published in 1959. Its rule: “A delay in a critical job will cause a comparable delay in the project completion time” [2]. Brooks put it in a manager’s terms: the network “shows who is on the critical path, where any slip moves the end date” [3].
2. How the two passes work
The forward pass walks the activity network from the start: each task begins as soon as its last predecessor finishes, giving its earliest start and the project’s shortest length. The backward pass walks back from that finish: each task must end before its first successor has to start, giving its latest finish. Float is the window between the two, minus the duration. Tools do the arithmetic; the manager reads the result.
3. Example: the last nine weeks of Quill
Quill is a fictional word processor, nine weeks from going live at a publishing house. Three streams of work merge into one acceptance run (durations in weeks).
The passes give each task its float, in weeks:
| Task | Total | Free | What it means for the manager |
|---|---|---|---|
| A, B, G | 0 | 0 | Critical: a week lost here is a week lost on go-live |
| C. Set up EU data centre | 1 | 0 | One spare week, shared with D |
| D. Cloud sync | 1 | 1 | The week is D’s only if C finishes on time |
| E. Citation styles | 4 | 0 | Dana may slip four weeks, but every week she takes is F’s |
| F. Accessibility review | 4 | 4 | The reviewer’s four weeks are his alone |
The critical path is A–B–G, nine weeks. For example, the vendor’s PDF engine arriving a week late moves go-live by a week; setting up the data centre a week late moves nothing, but leaves cloud sync no margin.
4. Total float and free float
Kelley and Walker defined four kinds of float [2]; managers use two [1]:
- Free float is “the range of dates in which an activity can finish without causing a delay in the early schedule of any activities that are its immediate successors.”
- Total float is “the range of dates in which an activity can finish without delaying the project completion date.”
Total float belongs to the path: “Slack is not additive along a path; it must be shared by all activities on the path” [4]; the first task to spend it takes it from the ones after. So free float is the one for task-level decisions: a developer can spend it without disturbing anyone. Quill’s E and F show the same four weeks of total float, yet only F’s are its own. Before telling someone they have float, say which kind.
5. Near-critical paths
A path nearly as long as the critical one deserves the same attention: “It is very likely that this near-critical path may actually drive the project completion date even though the total path length is less than that of the critical path” [1]. Quill’s C–D path is one week short, and PERT and merge bias shows why that week is thinner than it looks. The critical path also moves when a task changes, so recheck it after every change.
6. When to use it, and where it misleads
Use it to decide where money and attention go. On DuPont’s first test, a $10 million plant with 393 jobs, “only a very few jobs were critical - about 10% - and only these needed expediting”: two months came off the schedule at no extra cost, and two more for a 1% rise in direct cost [2].
The limits are built in. The passes assume known durations and that anyone can start any task the moment it is free. The computed date is therefore a lower bound: PERT shows why uncertainty pushes it later, and resource planning why people do.
How solid is this?
- Where it comes from. The inventors’ own report, whose DuPont figures are self-reported with no independent comparison; a practitioner textbook; a defence-acquisition primer.
- What is contested. Slack definitions drift; one textbook joins free and total float with “or” [5]. The Quill network is constructed for teaching.
Acknowledgments
This page adapts material from lectures by Eduardo Miranda [6] on software project management.
References
- R. K. Wysocki and R. McGary,Effective Project Management: Traditional, Adaptive, Extreme, 3rd ed. Wiley Publishing, 2003.
- J. E. Kelley Jr. and M. R. Walker,“Critical-Path Planning and Scheduling,” in Papers Presented at the December 1–3, 1959, Eastern Joint IRE-AIEE-ACM Computer Conference, ACM, 1959, pp. 160–173. doi: 10.1145/1460299.1460318.
- F. P. Brooks,The mythical man-month (anniversary ed.). Addison-Wesley Longman Publishing Co., Inc., 1995.
- C. L. Hoover, M. Rosso-Llopart, and G. Taran,Evaluating Project Decisions: Case Studies in Software Engineering. Addison-Wesley Professional, 2010. [Online]. Available: https://www.oreilly.com/library/view/evaluating-project-decisions/9780321685629/
- E. Miranda,“Managing Software Development.” 2014.