Velocity and flow

Velocity is the amount of work a team completes in a sprint, found by adding the sizes of the backlog items finished by its end [1]. Flow metrics ask a different question: how long one item takes, and where it waits.

A partly finished item counts zero. “Velocity measures output (the size of what was delivered), not outcome (the value of what was delivered)” [1], which is why it plans well and judges badly.

1. Why agile teams measure at all

Agile tracking is sometimes described as avoiding prediction. A review of 30 industrial studies says otherwise: teams used metrics for planning, progress tracking, quality, fixing process problems and motivation, and velocity was the most reported metric, in 15 of the 30 [2]. “Projects and sprints need to be planned and tracked.” Forecasting is one of the main reasons.

What differs is who owns the number: “In Agile mindset, estimating is applied as a way to predict how much the team can get done to guide sprint planning—not as a target that should be achieved as closely as possible” [2].

2. What velocity forecasts: a range of sprints

Points left divided by velocity gives the sprints remaining. Quote it as a range: “Using a range allows us to be accurate without being overly precise.” For example, a 200-point release at 17 to 20 points a sprint needs 10 to 12 sprints, not 10 [1].

A velocity forecast is the average so far, projected, so re-forecast every sprint and plan from capacity when a sprint is unusual. WMS Gaming scoped a release at half its velocity, leaving room for urgent defects [2].

Use velocity to forecast a stable team’s release from a sized backlog. Do not use it to compare teams, to judge people, or where there is no release to burn down; there, use flow (§4).

3. How velocity stops forecasting

Once a metric is used to evaluate a team, “the value of the metric moves toward the desired value” [3]. Three pressures make velocity a target:

  • A target from above. An executive tells Rubin: “Last year my team’s velocity averaged 30 points per sprint. This year I’m expecting the team to achieve 35 points per sprint.” Velocity rises to a plateau and dips with every change of people or tools [1], so the team can reach 35 only by inflating its point sizes [4].
  • Someone watching the number. At ThoughtWorks, managers “excused the developers from writ[ing] tests, and the testers cut on the thoroughness of the testing in hopes to maintain the velocity” [2]. Velocity held and quality paid.
  • A deadline. On a newspaper-site project, the team planned about 42 points in sprint 6 and finished about 29: it “succumbed to the pressure of approaching deadline and promised to deliver more functionality than actually possible” [5].

In each case the number stopped describing the team, so it stopped forecasting. The general pattern is on Process metrics. Here the rule is narrow: plan from the team’s own actuals, and when velocity drops, ask what changed before asking who is slow.

4. Flow: lead time, cycle time and cumulative flow

Lead time runs from an item’s request to its delivery; cycle time from the start of work to done. They matter most in maintenance and support, where work arrives continuously and no release backlog exists to burn down [4].

A cumulative flow diagram stacks one band per state over time. The top edge is all the work, the bottom band is done, and the bands between hold unfinished work: it is a burn-up with the middle opened up [6]. Read across a band for how long items stay in that state, and up through it for how many sit there. When a middle band widens, work is waiting there, not progressing. Little’s Law links those two readings.

The remedy is usually to start less. BBC Worldwide cut lead time by 37% and delivery variance by 47% after starting fewer features at once [7]; Timberline limited work to two features at a time [2]. The method behind this is Kanban.

How solid is this?

  • Where it comes from. Definitions from a practitioner textbook [1]; industrial practice from a review of 30 studies, 60% of them single cases and a fifth from Ericsson [2]. ThoughtWorks is its only strong case of velocity as a target.
  • What is contested. Whether extrapolating velocity forecasts well. A velocity date and an earned-value date are the same calculation [8], and extrapolating either “may be misleading” on non-linear agile work [6]. Hence a range, re-forecast every sprint.
  • What we do not hold. No study showing that cumulative flow diagrams improve delivery; the BBC result is one team with no control group.

Acknowledgments

This page adapts material from lectures by Eduardo Miranda and David Root [9], [10] on software project management.

References

  1. K. S. Rubin,
    Essential Scrum: A Practical Guide to the Most Popular Agile Process. Addison-Wesley, 2012.
  2. E. Kupiainen, M. V. Mäntylä, and J. Itkonen,
    “Using Metrics in Agile and Lean Software Development – A Systematic Literature Review of Industrial Studies,” Information and Software Technology, vol. 62, pp. 143–163, 2015, doi: 10.1016/j.infsof.2015.02.005.
  3. E. Bouwers, J. Visser, and A. van Deursen,
    “Getting What You Measure,” Communications of the ACM, vol. 55, no. 7, pp. 54–59, 2012, doi: 10.1145/2209249.2209266.
  4. K. S. Rubin,
    Essential Scrum: A Practical Guide to the Most Popular Agile Process. in Addison-Wesley Signature Series (Cohn). Addison-Wesley Professional, 2012. [Online]. Available: https://innolution.com/essential-scrum
  5. V. Mahnič and N. Žabkar,
    “Measuring Progress of Scrum-based Software Projects,” Elektronika ir Elektrotechnika, vol. 18, no. 8, pp. 73–76, 2012, doi: 10.5755/j01.eee.18.8.2630.
  6. A. Cabri and M. Griffiths,
    “Earned Value and Agile Reporting,” in Proceedings of AGILE 2006 (AGILE’06), IEEE, 2006, pp. 17–22. doi: 10.1109/AGILE.2006.21.
  7. P. Middleton and D. Joyce,
    “Lean Software Management: BBC Worldwide Case Study,” IEEE Transactions on Engineering Management, vol. 59, no. 1, pp. 20–32, 2012, doi: 10.1109/TEM.2010.2081675.
  8. T. Sulaiman, B. Barton, and T. Blackburn,
    “AgileEVM – Earned Value Management in Scrum Projects,” in Proceedings of AGILE 2006 (AGILE’06), IEEE, 2006, pp. 7–16. doi: 10.1109/AGILE.2006.15.
  9. E. Miranda,
    “Managing Software Development.” 2014.
  10. D. Root,
    Managing Software Development. Carnegie Mellon University / Innopolis University lecture series, 2014.