SN L4b — Estimation

A revision summary of the second Scope lecture. An estimate is “the information we use to evaluate the cost of a future decision” [1], so every number in the lecture answers two questions: how much, and how sure are you? The running example is Workopolis, a job board with fifteen user stories for job seekers, recruiters and the site owner, and the lecture estimates it four ways. Each section links to the handbook page carrying the detail and the sources.

1. Why estimates go wrong

A review of ten surveys puts the typical cost overrun between 30 and 40%; Standish’s famous 89% is the outlier [2], [3]. So a 1,000-hour estimate means 1,300 to 1,400 hours expected: carry the difference, or say why you will beat the average.

Three numbers have three owners. The estimate is what you believe, the target is what they want, the commitment is what you promise, the estimate plus contingency. The estimate feeds the budget; it is not the budget [4] [5].

An early estimate is a range. At the initial concept, the real effort can be anywhere from 0.25 to 4 times the most likely number, a spread of 16 to 1; after requirements it is still about ±50%, and it narrows only as the work is done [6]. Give every estimate as a range, say the phase, and name the milestone of the next one.

When the budget comes first, the estimate’s job changes. You are given 600 hours to build Workopolis with Scrum: call 600 the budget, estimate independently at six effective hours a day, and if the estimate is bigger, cut stories in the product owner’s order [6]. Section 6 answers the question.

Exam tip: given a sponsor’s number, first say which of the three it is. A deadline is a target.

→ Estimates · Estimation approaches

2. The map of methods

Scope becomes size, size becomes effort, effort becomes schedule. The size is the box everything hangs from: “the most significant input to the COCOMO II model is Size” [7].

Miranda groups estimation methods into six families [4], and each sits somewhere on that chain:

Family The number comes from Gives
Judgment a person: alone, in a group, or comparing pairs size in points, or hours
Engineering a cost function built from what drives the work effort
Counting a weighted count of what the user gets size
Industry norms a published ratio effort, from a size
Analogy the nearest finished projects (10 to 12 of them) effort
Parametric a formula fitted to past projects effort, from a size

What separates them is the last step: “the quantification step—that is, the final step that transforms the input into the effort estimate” [8]. A person takes it, or a formula does.

→ Estimates · Estimation approaches

3. Expert judgment

An expert works top-down, against finished projects, or bottom-up, summing the WBS activities. Across seven teams, bottom-up was off by 23% and top-down by 45%; top-down did well only when the estimator recalled a very similar project [9]. Know a similar project? Go top-down. If not, decompose.

Judgment has known biases. In one experiment, a single sentence from a manager who admitted having no experience moved the mean estimate from 8.3 months to 17.4 with a 20-month anchor [10]. So nobody, the sponsor included, says a number before the estimators have written theirs.

Each bias has a fix that changes the input: a checklist against availability, a number-free brief against anchoring, many past tasks against representativeness, an independent second estimate against confirmation. All four feed overconfidence: professionals’ 90% ranges held only 35% of the time [11].

→ Expert judgment

4. Estimating as a group

Planning Poker gives each estimator a card to pick privately; all cards turn over together; if they differ, the highest and lowest explain, and the team votes again. Grenning’s deck is 1, 2, 3, 5, 7, 10 and ∞, where ∞ means split it, and his purpose is plain: “Precision of individual estimates is not the goal. Determining the project scope is” [12]. No averages, no numbers off the deck [13].

Eduardo’s Variation, this course’s version, agrees a medium story as the baseline first, discusses coincidences as well as differences, records every estimator’s final card, and probes unusual disagreement instead of averaging blindly [4].

A uniform-looking backlog is not. One senior developer sized all fifteen Workopolis stories; with Search jobs at 5, Register came out 14 times Log out, and the same expert gave Register 14.4 in one session and 13.0 in the next [14].

Poker removes the first speaker’s anchor and brings in the quiet members, but not the first round’s: “We found no story having the final planning poker estimate outside these boundaries” [15]. Matching cards end the talk even when the reasons differ, and on unfamiliar stories Poker did worse than plain discussion [16]. If the talk reveals new work, vote again from zero.

Paired comparisons ask only how much bigger is X than Y? and then check how consistent the answers are [17] [14]. For an architecture item unlike the rest of the backlog, compare it with an item of known size, or estimate it bottom-up.

Story points are easy to agree on, because people compare better than they measure, and hard to compare: a point means something in one team against one reference, becomes a date only through velocity, and inflates once velocity is rewarded [13]. On ten Workopolis stories, comparing each with all the others gave a project total of 44.6; comparing each with only two gave 99.7 [14]. Compare each story with at least four others. And 65 points is not a number of hours, and another team’s 65 is a different 65. When the sponsor needs hours, or a size an outsider can check, you need a different unit.

Exam tip: “Poker prevents anchoring” is half right. It removes the first speaker’s anchor; the first round’s cards then fence the result.

→ Planning Poker · Paired comparison

5. Function points

Lines of code are a poor size for an estimate: they do not exist when the estimate is due, and they differ for the same function in another language [18]. Function points count what the user gets (inputs, outputs, inquiries and files), from the requirements, and the same screens score the same in C++ or in Clarion [19].

Two questions classify every transaction. Does it change a stored file? Then it is an external input (EI) [19]. If not, does it derive data? Then an external output (EO); otherwise an external inquiry (EQ). For files, count kinds of subgroup, never records: a department holding 20 employees has two record types [20].

Example: Workopolis, counted. User stories carry no field lists, so every item is rated Average (the count is constructed for the course; the stories are Miranda, Bourque & Abran’s [14]):

Type Workopolis n × weight FP
ILF, kept job seeker (profile and resume as two record types), career alert, job announcement 3 × 10 30
EIF, only read recruiter accounts: no story creates or changes them 1 × 7 7
EI register; upload, delete resume; create, suspend, delete alert; post, edit, delete job 9 × 4 36
EQ search jobs; two log-ins 3 × 4 12
EO notify job seekers: an e-mail with the count of matches 1 × 5 5
  log-outs move no data: not counted   90

The choices move the count a little: alerts folded into the job seeker give 80, Notify without a count (EQ) 89, recruiters as a kept file 93. Write each choice down.

From size to hours, with your own rate. At an example company’s 8 to 12 FP per person-month, 90 FP is 7.5 to 11.3 person-months, or 1,200 to 1,800 hours at 160 hours a month. Say what the rate covers: here requirements to acceptance, management included, but not deployment, training or support. Read backwards, the sponsor’s 600 hours buys 30 to 45 FP, a third to a half of Workopolis.

A second route: COCOMO II. Effort is PM = A × Size^E × ΠEM, with A = 2.94 fitted to 161 projects [7]. COCOMO wants lines of code, so it converts function points per language: 53 lines per point in Java, so 90 FP is 4.8 KSLOC. With every driver nominal, E = 1.10 and the effort is 2.94 × 4.81.10 ≈ 16 person-months, about 2,500 hours. E above one means twice the system is more than twice the work. Uncalibrated, the model applies other projects’ productivity to yours; recalibrate A on five of your own before quoting it [7].

The count is reliable; an estimate from it is not. Two trained counters differ by a median of 12% [21], while Albrecht’s formula from function points to effort typically missed one project by about 85% [22]. Quote the effort as a range.

→ Function Point Analysis · FPA explained · COCOMO · Workopolis, rated in full

6. Combining methods

In the 2009 debate, Jørgensen argued that an expert uses what no model takes in, and Boehm that a model “doesn’t modify its estimates when customers, managers, or marketers apply pressure” [8]. Across fifteen studies the score was five, five and five [23]. Use a calibrated model to check the expert, not to replace them.

Rules of thumb are checks, not estimates. Capers Jones’s rules turn function points into schedule (FP0.4 months), team size (FP ÷ 150) and defects (FP1.25), and he warns that they “should not be used for contracts, bids, or other serious business purposes” [24]. On Workopolis: 900.4 ≈ 6 months × 90 ÷ 150 ≈ 0.6 people, about 3.6 staff months or 580 hours. Before trusting a norm, ask which hours and activities it counts.

Combine independent estimates, then read the spread. On one real project, individuals averaged 1,088 hours, mixed groups 1,548, and the project took 2,365 [25]. A wide spread usually means the scope was misread or the productivity data is wrong [26]. With little history: two or three people estimate alone, top-down from a norm and bottom-up over the WBS, check with a model or a rule, report a range, and start recording actuals.

Workopolis, side by side. Planning Poker: 65 points, no hours until the team has a velocity. Jones’s rules: about 580 hours. Function points at the team’s own rate: 1,200 to 1,800 hours. COCOMO, nominal and uncalibrated: about 2,500 hours. A fourfold spread is a diagnosis, not something to average: the norm counts less work, the model carries other people’s productivity. Build the estimate on your own history and use the others as its fences. The 600 hours is what a rule of thumb gives, so the honest options are to commit the range or to cut to the stories worth 30 to 45 FP.

→ Estimation approaches · Expert judgment

Practice questions

1. Why should an estimator never hear the budget before estimating, and what should happen when the budget is fixed first?

Answer

A budget is a target, and a number heard first anchors the estimate [10]. Estimate independently, then treat the gap as a scope decision for the product owner [6].

2. Why is a function-point count more trustworthy than an effort estimate made from it?

Answer

Trained counters differ by a median of 12% [21]. The step from size to effort leaves out the team, the technology and hidden complexity, so on one project Albrecht’s formula typically missed by about 85% [22].

3. What does Planning Poker fix, and what does it leave unfixed?

Answer

Private cards remove the first speaker’s anchor and bring in the quiet members. The first round still fences the final estimate [15], and matching cards end the discussion even when the reasons differ, which Eduardo’s Variation targets by discussing coincidences [4].

4. Workopolis came out at 580, 1,200–1,800 and 2,500 hours by three methods. Which do you report, and why not the average?

Answer

The 1,200–1,800 range, because it rests on the team’s own delivery rate. The spread says the methods count different things: Jones’s norm an unstated set of activities, COCOMO other organisations’ productivity until it is calibrated [7]. Averaging hides that diagnosis [26].

5. “Our team tried COCOMO and it was useless.” What would you ask before agreeing?

Answer

Was it calibrated on our own projects, and run with its cost drivers? Without drivers it landed within 1.3 times the actuals 29% of the time; with them, 78% [8]. An uncalibrated model is a cross-check at best.

Where this goes next

Workopolis has a range; the sponsor still wants a date. Do you commit to the whole scope up front, or one sprint at a time? That is the next lecture.


Acknowledgments

This content is heavily inspired by and adapted from lectures by Eduardo Miranda and David Root [27] on software project management. The commitment-level planning picture, the six families, the 600-hour exercise, the Workopolis stories and Eduardo’s Variation of Planning Poker are Miranda’s [4].

References

  1. C. L. Hoover, M. Rosso-Llopart, and G. Taran,
    Evaluating Project Decisions: Case Studies in Software Engineering. Addison-Wesley Professional, 2010. [Online]. Available: https://www.oreilly.com/library/view/evaluating-project-decisions/9780321685629/
  2. K. Moløkken and M. Jørgensen,
    “A Review of Surveys on Software Effort Estimation,” in Proceedings of the 2003 International Symposium on Empirical Software Engineering (ISESE 2003), IEEE Computer Society, 2003, pp. 223–230. doi: 10.1109/ISESE.2003.1237981.
  3. J. L. Eveleens and C. Verhoef,
    “The Rise and Fall of the Chaos Report Figures,” IEEE Software, vol. 27, no. 1, pp. 30–36, 2010, doi: 10.1109/MS.2009.154.
  4. E. Miranda,
    “Managing Software Development.” 2014.
  5. S. Grimstad, M. Jørgensen, and K. Moløkken-Østvold,
    “Software Effort Estimation Terminology: The Tower of Babel,” Information and Software Technology, vol. 48, no. 4, pp. 302–310, Apr. 2006, doi: 10.1016/j.infsof.2005.04.004.
  6. S. McConnell,
    Rapid development: taming wild software schedules. Pearson Education, 1996.
  7. Center for Software Engineering, USC,
    COCOMO II Model Definition Manual. Center for Software Engineering, University of Southern California, 2000.
  8. M. Jørgensen, B. Boehm, and S. Rifkin,
    “Software Development Effort Estimation: Formal Models or Expert Judgment?,” IEEE Software, vol. 26, no. 2, pp. 14–19, Mar. 2009, doi: 10.1109/MS.2009.47.
  9. M. Jørgensen,
    “Top-down and Bottom-up Expert Estimation of Software Development Effort,” Information and Software Technology, vol. 46, no. 1, pp. 3–16, Jan. 2004, doi: 10.1016/S0950-5849(03)00093-4.
  10. J. Aranda and S. Easterbrook,
    “Anchoring and Adjustment in Software Estimation,” in Proceedings of the 10th European Software Engineering Conference Held Jointly with 13th ACM SIGSOFT International Symposium on Foundations of Software Engineering (ESEC/FSE ’05), ACM, Sept. 2005, pp. 346–355. doi: 10.1145/1081706.1081761.
  11. T. Halkjelsvik and M. Jørgensen,
    “From Origami to Software Development: A Review of Studies on Judgment-Based Predictions of Performance Time,” Psychological Bulletin, vol. 138, no. 2, pp. 238–271, 2012, doi: 10.1037/a0025996.
  12. J. W. Grenning,
    “Planning Poker or How to Avoid Analysis Paralysis while Release Planning.” Renaissance Software Consulting, Apr. 2002. Accessed: Oct. 11, 2026. [Online]. Available: https://wingman-sw.com/papers/PlanningPoker-v1.1.pdf
  13. K. S. Rubin,
    Essential Scrum: A Practical Guide to the Most Popular Agile Process. in Addison-Wesley Signature Series (Cohn). Addison-Wesley Professional, 2012. [Online]. Available: https://innolution.com/essential-scrum
  14. E. Miranda, P. Bourque, and A. Abran,
    “Sizing User Stories Using Paired Comparisons,” Information and Software Technology, vol. 51, no. 9, pp. 1327–1337, Sept. 2009, doi: 10.1016/j.infsof.2009.04.003.
  15. V. Mahnič and T. Hovelja,
    “On Using Planning Poker for Estimating User Stories,” Journal of Systems and Software, vol. 85, no. 9, pp. 2086–2095, Sept. 2012, doi: 10.1016/j.jss.2012.04.005.
  16. N. C. Haugen,
    “An Empirical Study of Using Planning Poker for User Story Estimation,” in Proceedings of AGILE 2006 Conference (AGILE’06), IEEE Computer Society, 2006, pp. 23–34. doi: 10.1109/AGILE.2006.16.
  17. E. Miranda,
    “Improving subjective estimates using paired comparisons,” IEEE Software, vol. 18, no. 1, pp. 87–91, Jan. 2001, doi: 10.1109/52.903173.
  18. R. E. Park,
    “Software Size Measurement: A Framework for Counting Source Statements,” Software Engineering Institute, Carnegie Mellon University, Technical Report CMU/SEI-92-TR-020, Sept. 1992. doi: 10.21236/ADA258304.
  19. D. Longstreet,
    Function Points Analysis Training Course. Longstreet Consulting Inc.
  20. N. Gunti,
    “Function Point Analysis Examined,” Avenue A | Razorfish, White paper, Sept. 2006.
  21. C. F. Kemerer,
    “Reliability of Function Points Measurement: A Field Experiment,” Communications of the ACM, vol. 36, no. 2, pp. 85–97, Feb. 1993, doi: 10.1145/151220.151230.
  22. A. J. Albrecht and J. E. Gaffney Jr.,
    “Software Function, Source Lines of Code, and Development Effort Prediction: A Software Science Validation,” IEEE Transactions on Software Engineering, vol. SE-9, no. 6, pp. 639–648, Nov. 1983, doi: 10.1109/TSE.1983.235271.
  23. M. Jørgensen,
    “A Review of Studies on Expert Estimation of Software Development Effort,” Journal of Systems and Software, vol. 70, no. 1–2, pp. 37–60, Feb. 2004, doi: 10.1016/S0164-1212(02)00156-5.
  24. C. Jones,
    “By Popular Demand: Software Estimating Rules of Thumb,” Computer, vol. 29, no. 3, pp. 116–118, Mar. 1996, doi: 10.1109/MC.1996.485905.
  25. K. Moløkken-Østvold and M. Jørgensen,
    “Group Processes in Software Effort Estimation,” Empirical Software Engineering, vol. 9, no. 4, pp. 315–334, Dec. 2004, doi: 10.1023/B:EMSE.0000039882.39206.5a.
  26. R. S. Pressman,
    Software Engineering: A Practitioner’s Approach, 7th ed. McGraw-Hill, 2010.
  27. D. Root,
    Managing Software Development. Carnegie Mellon University / Innopolis University lecture series, 2014.