Kanban

Kanban is a pull system with explicit limits on work in progress, laid over whatever process a team already runs. It prescribes no roles and no ceremonies: work is visualised on a board, each stage is given a cap, and nothing new is pulled into a stage until something leaves it.

The name is the Japanese 看板, billboard. The board is what people notice — but the board is not the method. The limit is the method. A team that visualises its work and admits it without a cap has a nicer wall and the same queue.

1. Cap the queue and the bottleneck shows itself

A Kanban board with WIP limits on the Ready, In Development and In Test columns; Development is full at 3 of 3, so the pull from Ready is blocked

Development is full at 3/3, so nothing new is started until Test frees up. The numbers on the headers are the method.

The mechanism is queueing, not effort. Consider a pipeline that accepts 10 requirements a week, develops 10 a week, and tests 5 a week. Nobody is idle or underperforming, yet work accumulates in front of testing indefinitely — and adding developers makes it worse.

Cap the testing queue and development cannot pull new work once the cap is reached. Developers stop starting things, and the constraint becomes visible to everyone rather than surfacing later as a missed date.

A WIP limit is an entry criterion on a stage, which is exactly what ETVX formalises [1] — the board just makes it impossible to ignore. Limits come from the bottlenecks a team observes, not from a template [2].

2. Start less, finish sooner

Example — the BBC Worldwide Digi-Hub team. Nine people in London adopted lean and Kanban and were measured over twelve months [2]:

  Before After
Features started 84 64 (−24%)
Lead time — −37%
Lead-time variability 70.7 days 37.3 days
Customer-reported defects 2.9/week 2.2/week

The first row explains the others. The team started 24% fewer things and cut them smaller — the share classified as small rose from 52% to 75% — and lead time and predictability followed.

Read that carefully: the gain is flow and predictability, not volume. A manager who reads −37% lead time as “more work done” has it backwards, and managers are usually rewarded for starting things, which is what makes this worth teaching.

Do not say throughput rose because WIP fell. The paper states that output value “cannot be measured exactly” and reports that the team believed more value was delivered. What was measured is that cycle time fell as WIP fell.

3. Where it fits, and how it differs from Scrum

The graded question is what kind of project suits Kanban, and the cited answer is maintenance and support. Ken Rubin puts the sweet spots for Kanban in “the software maintenance and support areas”, and gives the reason from the other side: “Scrum is not well suited to highly interrupt-driven work… In interrupt-driven environments you would be better off considering an alternative agile approach called Kanban” [3]. One organisation can reasonably run both — Scrum for new-product development, Kanban for support.

Carry the hedge with it: Rubin notes in the next breath that some practitioners argue Kanban’s focus on eliminating overburden makes it appropriate in complex domains too.

The difference fits in one sentence: both cap work in flight, but they cap different things. Scrum caps time — the sprint — and lets scope settle inside it; Kanban caps queue depth and lets time settle. Timeboxing is itself a WIP limit [3], which makes them complements rather than rivals. On adaptation they diverge sharply: Kanban starts from the existing process, where the Scrum Guide calls its framework immutable [4].

Under AI agents. If code generation accelerates while review does not, work accumulates at review — so the WIP limit that binds moves downstream. This is the BBC result run backwards, and it is the same law; see agentic.

How solid is this?

  • The evidence is one team, one company, twelve months, no control group. The authors say the hypothesis was “supported by this single case study” [2]. Nothing here shows Kanban beats Scrum.
  • It is confounded, and that is our reading rather than theirs. In the same period the team also rewrote legacy code and reduced turnover — equally good candidate causes of the defect drop, which the authors hedge as “possibly due to the improving structure of the code base”.
  • One figure is reported two ways — the abstract says consistency rose 47%, the body says lead-time variability fell 47%, from 70.7 to 37.3 days. Use the body’s absolute numbers.
  • The release-frequency figure often quoted from this paper (2/month to 16/month) compares two single months about two years apart, outside the study window. Leave it alone.
  • Rubin is a practitioner book by a Scrum trainer [3]; his Kanban material is definitional, not evidential.

Acknowledgments

This page adapts material from lectures by Eduardo Miranda and David Root [5] on software project management.

References

  1. R. A. Radice, N. K. Roth, A. C. O’Hara, and W. A. Ciarfella,
    “A programming process architecture,” IBM Systems Journal, vol. 24, no. 2, pp. 79–90, 1985, doi: 10.1147/sj.242.0079.
  2. P. Middleton and D. Joyce,
    “Lean Software Management: BBC Worldwide Case Study,” IEEE Transactions on Engineering Management, vol. 59, no. 1, pp. 20–32, 2012, doi: 10.1109/TEM.2010.2081675.
  3. K. S. Rubin,
    Essential Scrum: A Practical Guide to the Most Popular Agile Process. in Addison-Wesley Signature Series (Cohn). Addison-Wesley Professional, 2012. [Online]. Available: https://innolution.com/essential-scrum
  4. K. Schwaber and J. Sutherland,
    “The Scrum Guide.” Nov. 2020. [Online]. Available: https://scrumguides.org/docs/scrumguide/v2020/2020-Scrum-Guide-US.pdf
  5. D. Root,
    Managing Software Development. Carnegie Mellon University / Innopolis University lecture series, 2014.

Disclaimer: AI is used for text summarization, polishing and explaining. Authors have verified all facts and claims. In case of an error, feel free to file an issue.