Process Metrics
A process metric measures how work gets done — cycle time, defect-removal rate, review coverage — rather than what was built. It exists to improve the process, and it stops working the moment it is used to judge the people running it.
That last sentence is the whole difficulty. A product metric sits still while you measure it. A process metric is attached to people who can see it, and who will respond.
1. Measure the process, but never the people
Watts Humphrey, writing the maturity framework the whole improvement movement is built on, states the rule as an absolute: “Process data must not be used to compare projects or individuals. Its purpose is to illuminate the product being developed and to provide an informed basis for improving the process” [1]. He gives the consequence rather than a complaint — “When such data is used by management to evaluate individuals or teams, the reliability of the data itself will deteriorate” — and then the mechanism underneath it: “Perhaps most important is that the mere act of measuring human processes changes them.”
So the question a manager answers before choosing any metric is not is this the right number but who will see it, and what will happen to them because of it.
2. Precision is not the defence
The intuitive fix is a better metric — define it more tightly, compute it more carefully. The evidence says that misses the mechanism. Douglas Hoffman’s account of metrics dysfunction is that it appears “whether or not our models are correct, and regardless of how well or poorly we collect and compute” the numbers [2]. Gaming is a response to what the number is used for, and no amount of definitional care changes that.
Example — closing twenty-five defects without fixing one. A team was measured on defect reports closed. Twenty-five open reports were closed as duplicates of a single new report whose only shared property with them was the subsystem it was filed against; the new “master” report’s description simply pointed back at all twenty-five [2]. Nobody falsified anything, the count improved, and the defects were still there. A second team, measured on the age of open defects, reassigned a dozen long-running ones — resetting the clock without touching the code.
The software-specific version students will meet is velocity. When a team’s points-per-sprint becomes a target, estimates inflate or work gets called done early [3]. Steve McConnell names the two failure modes directly — “overoptimization of single-factor measurements” and “misuse of measurements for employee evaluations” — and notes that a badly run metrics programme “can actually damage developer morale” [4].
3. Two numbers are rarely comparable
Even honestly gathered, process data resists comparison. Humphrey puts task-complexity variation across product types at more than five to one, small modifications at two to three times the cost of new code per line, and variation from differing definitions alone at “at least as high as seven times” [1]. Two teams reporting different numbers may be doing different work, or counting differently. Ranking them says nothing.
4. What to do instead
Derive the metric from a goal rather than from what is easy to collect — that is GQM [5]. Then decide the audience deliberately: data that reaches the team improves the process, and the same data reaching an appraisal destroys it. Where the thing that matters cannot be counted at all, the scoreboard tracks judgement as a trend instead of inventing a number.
Measurement is also not free. Humphrey again: “Measurements are both expensive and disruptive; overzealous measuring can degrade the processes we are trying to improve.”
How solid is this?
- Nothing cited here measures a measurement programme’s effect. These sources establish that the behaviours happen, not how often, and not that metrics are harmful on balance. The conclusion is choose the audience, not stop measuring.
- Hoffman’s paper is a practitioner conference talk (PNSQC 2000), and its cases are anecdotes he states he altered to protect the organisations involved. No frequencies, no sampling [2].
- Humphrey’s material is from 1988, reprinted as Appendix A of the SEI’s SEPG Guide — so cite it to Humphrey, not to Fowler & Rifkin, who edited the volume [1]. His figures are a snapshot of that era’s data.
- McConnell and Rubin are practitioner books — well-grounded advice, not studies [4] [3].
Acknowledgments
This page adapts material from lectures by Eduardo Miranda and David Root [6] on software project management.
References
- P. Fowler and S. Rifkin,“Software Engineering Process Group Guide,” 1990.
- D. Hoffman,“The Darker Side of Metrics,” in Pacific Northwest Software Quality Conference (PNSQC), 2000.
- K. S. Rubin,Essential Scrum: A Practical Guide to the Most Popular Agile Process. in Addison-Wesley Signature Series (Cohn). Addison-Wesley Professional, 2012. [Online]. Available: https://innolution.com/essential-scrum
- S. McConnell,Rapid development: taming wild software schedules. Pearson Education, 1996.
- V. R. Basili, G. Caldiera, and H. D. Rombach,“The Goal Question Metric Approach,” in Encyclopedia of Software Engineering, John Wiley & Sons, 1994.
- D. Root,Managing Software Development. Carnegie Mellon University / Innopolis University lecture series, 2014.